Groundwater Well Installation Work Plan Sharpe Army Depot <br /> Lathrop, California <br /> The wells will also be protected by three or more bollards of concrete-filled, 4-inch-diameter steel pipe <br /> cast surrounding the installed well. <br /> Monitoring Wells <br /> For onsite monitoring wells (MW549C and MW550C), a 6-inch diameter locking steel casing set into a <br /> concrete pad (2 to 4 ft square pad)will be installed around each well casing the top of the steel casing will <br /> be set approximately 3 ft above the ground surface. The stickup (steel casing) diameter will be 6 inches. <br /> The concrete pad will be sloped from the edge of the steel casing to the edge of the pad and smoothed <br /> with a trowel to facilitate the flow of surface water away from the well.The well will also be protected by <br /> three or more bollards of concrete-filled, 4-inch-diameter steel pipe cast surrounding the installed well. <br /> For offsite monitoring wells (MW551B/C and MW552C), the completions will be flush mounted to an <br /> elevation similar to that of the surrounding street. A traffic-rated 16-inch diameter steel casing and lid <br /> completion will be installed. The concrete apron will be sloped from the edge of the steel casing to the <br /> edge of the pad and smoothed with a trowel to facilitate the flow of surface water away from the well. <br /> 3.2.5 Conveyance Piping Installation and Electrical Hook-up <br /> Preliminary conveyance piping line routes are shown on Figures 13 and 14. Final conveyance line locations <br /> will be determined after negotiations with UPRR. <br /> Extraction wells EWC6 and EWC7 will be connected to the existing contaminated-water conveyance piping <br /> that runs to the South Balloon GWTP (Figure 13). Electrical and communications conduits will be installed <br /> to allow connection of the new wells to the existing electrical power supply and allow for connection to <br /> the GWTP control systems. EWC6 is located approximately 800 ft southwest of the existing well EWC5, as <br /> shown in Figure 13. EWC7 is located about 200 ft northwest of the existing well EWC5, as shown in Figure <br /> 13. <br /> Extraction wells EWC8 and EWC9 will also be connected to the existing contaminated-water conveyance <br /> piping that runs to the South Balloon GWTP (Figure 13). Electrical and communications conduits will be <br /> installed to allow connection of the new wells to the existing electrical power supply and allow for <br /> connection to the GWTP control systems. EWC8 is located offsite approximately 100 ft northeast of <br /> MW543C on the east side of the UPRR tracks, and EWC9 is located offsite approximately 675 ft north of <br /> MW540C on the west side of the UPRR tracks. Conveyance piping to connect EWC8 to the South Balloon <br /> GWTP will require directional drilling beneath the UPRR tracks. <br /> Extraction well EWCC7 will be connected to the existing contaminated-water conveyance piping that runs <br /> to the Central Area GWTP (Figure 14). Electrical and communications conduits will be installed to allow <br /> connection of the new well to the existing electrical power supply and allow for connection to the GWTP <br /> control systems. EWCC7 is located approximately 550 ft southwest of the existing well MW514C and <br /> approximately 275 ft east of existing wells MW525C and EWC6, as shown in Figure 14. <br /> Trenching will be required to install the new conveyance piping and electrical and communications <br /> conduits, and the displaced soil will be managed as discussed in Section 3.3, "Waste Management." The <br /> new wells and trenching will not be located in areas of contaminated soils. <br /> Ahtna Environmental,Inc. 16 <br />