Task Duration Tentative Start and Finish Dates Apr, '16 May, '16 Jun, '16 Jul, '16 Aug, '16 Sep, '16 Oct, '16 Nov, '16 Dec, '16 Jan, '17 Feb, '17 Mar, '17 Apr, '17 May, '17 Jun, '17
<br /> Site Characterization
<br /> Workplan
<br /> SLP Submit Draft
<br /> Workplan to DTSC April 15,2015
<br /> DTSC Draft Workplan One Months April 15,2016 to May 15,2016
<br /> Comments
<br /> SLP Revise Draft Two Weeks May 15,2016 to May 30,2016
<br /> Workplan
<br /> SLP Submit Revised Draft
<br /> Workplan to DTSC May 30,2016
<br /> DTSC Revised Draft Two Weeks May 30,2016 June 15,2016
<br /> Workplan Review
<br /> SLP Submits Final One Week June 24,2016 0--0
<br /> Workplan
<br /> Final DTSC Letter Two Weeks June 24,2016 to July 8,2016
<br /> Site Characterization
<br /> Field Work
<br /> EHD Permits Two Weeks June 8,2016 to July 22,2016
<br /> AM
<br /> SLP Conduct Site Six Weeks July 22,2016 to September 1,2016
<br /> Characterization
<br /> Investigation
<br /> Report
<br /> SLP Prepare Draft Six Weeks September 1,2016 to October 15,2015
<br /> Investigation Report
<br /> SLP Submit Draft
<br /> kiestigation Report to DTSC October 15,2016
<br /> DTSC Draft Investigation Two Months October 15,2016 to December 15,2016
<br /> Report Comments
<br /> Quarterly Groundwater November 15,2016
<br /> Monitoring
<br /> Quarterly Groundwater December 15,2016
<br /> Monitoring Report
<br /> SLP Revise Draft Two Weeks December 15,2016 to December 30,2016
<br /> Investigation Report
<br /> SLP Submit Revised Draft December 30,2016
<br /> Investigation Report to DTSC
<br /> DTSC Revised Draft Two Weeks December 30,2016 to January 15,2017
<br /> Investigation Report Review
<br /> Second Indoor Air January 17-18,2017 •
<br /> Sampling
<br /> SLP Submits Final One Week January 23,2017 0-8
<br /> Investigation Report
<br /> Final DTSC Letter One Month February 23,2017
<br /> DTSC Commit Date February 23,2017
<br /> Risk Evaluation and
<br /> 0eanupLevelDetermination
<br /> Scoping Meeting February 28,2017
<br /> Community Profile
<br /> DTSC Prepares Two Weeks February 28,2017 to March 15,2017
<br /> Community Profile
<br /> Feasibility Study
<br /> (FS)
<br /> SLP Prepare Draft FS One Month March 15,2017 to April 15,2017
<br /> Quarterly Groundwater March 15,2017
<br /> Monitoring
<br /> Quarterly Groundwater April 15,2017
<br /> Monitoring Report
<br /> SLP Submit Draft FS April 15,2017
<br /> to DTSC
<br /> DTSC Draft FS Two Months April 15,2017 to June 15,2017
<br /> Comments
<br /> PARTNER Workplan Implementation
<br /> Schedule
<br /> Engineering and Science,Inc: Figure Prepared By Date
<br /> 2154 Torrance Boulevard,Suite 200 D1-1 KLF March 2016
<br /> Torrance,California 90501 3225 North Tracy Boulevard
<br /> Project Number: SM14-129814 Tracy,California 95376
<br />
|