Addendum to Proposed Remediation Well Installation Work Plan <br /> Stockton Charter Way Commingled Plume #CP0057 <br /> May 2, 2025 <br /> will be accomplished by alternately surging each well with a vented surge block followed by <br /> pumping (using a submersible pump) to remove accumulated sediment. Final purging will be <br /> performed with either a submersible pump or bailer, and pH, temperature, and conductivity will <br /> be measured at regular intervals during purging. Development will be considered complete <br /> when: 1) eight well volumes have been removed and physical-chemical parameter trends have <br /> stabilized over three consecutive measurements (<0.05 pH, 3%conductivity, and 10% <br /> temperature); 2) ten well volumes have been removed; or, 3) the well has been purged dry (if <br /> the well does not sustain flow or is slow to recover). <br /> Following well construction, a licensed land surveyor or registered civil engineer will survey newly <br /> installed wells. The tops of casings of wells will be surveyed within the California State Plane <br /> Coordinate System for horizontal and vertical control to meet the State of California Water <br /> Resources Control Board requirements. The coordinates will be referenced to a known <br /> benchmark according to the North American Datum of 1983 (NAD83) and the North American <br /> Vertical Datum of 1988 (NAVD 88). <br /> 2.2.1 Soil Samples <br /> Soil sampling will be conducted during the advancement of the boring for ART-1 1, similarly to the <br /> proposed sampling for ART-9 and ART-10.Soil samples will be screened in the field for the presence <br /> of VOCs using a PID, soil classifications, VOC measurements, sample intervals, and other pertinent <br /> geologic information. However, no samples will be submitted for laboratory analyses. <br /> 2.2.2 Waste Handling and Disposal <br /> Additional waste generated for ART-1 1 will be handled along with waste generated for ART-9 and <br /> ART-10. See previous Stantec workplan dated February 27, 2025, for waste disposal information. <br /> 2.2.3 Reporting <br /> Reporting for the installation and sampling of ART-1 1 will be documented in the same report with <br /> ART-9 and ART-10. See previous workplan dated February 27, 2025, for reporting details. <br /> 3.0 PROPOSED ART WELL REMEDIATION <br /> ART-1 1 will be added to the existing remedial program for the site, similarly to ART-9 and ART-10. <br /> See previous workplan dated February 27, 2025, for ART well remediation information. <br /> 5 Stantec 4 <br />