Woodbridge Irrigation District <br /> Fish Screen Project Description <br /> 2007-2008 <br /> Description of the Planned Construction of the"V" Screen <br /> The District's project consists of constructing a"V" type fish screen at the entrance of the <br /> District's intake canal on the Mokelumne River, thereby diverting out-migrating juvenile <br /> fish into a fish bypass pipeline at the WID diversion which returns them to the <br /> Mokelumne River downstream and prevents them from entering the District's canal <br /> system. The location of the project is shown in Exhibit "A"-Woodbridge Irrigation <br /> District Lower Mokelumne River Restoration Project. <br /> The "V" Screen Construction and canal lining within the County Right of Way <br /> This portion of the project is within the County right of way adjacent to and east of the <br /> Lower Sacramento Road Bridge in Woodbridge and is scheduled to begin on October 1, <br /> 2007 and be completed on May 1, 2008. The District project will involve lining the canal <br /> floor and walls with 2 feet of reinforced concrete and placement of a 1/2 inch expansion <br /> joint between the two structures. No structural changes will be made to the bridge. <br /> Modification of the curb to a kneel down side walk and vehicle gates. <br /> The District also plans to construct an approach on the SE corner of the bridge between <br /> the existing brick pilasters and modify the fence into a double door swinging and locking <br /> gate identical to the County's NE corner gate. The vehicle approach will consisting of <br /> first saw cutting and removing the existing curbing and then following the Type 2 <br /> Commercial Driveway Drawing (SJCO Drawing used to construct the NW corner vehicle <br /> approach on original bridge plan) constructing the kneel down curb. <br /> The County Public Works Department would be notified prior to construction and prior <br /> to placement of concrete concrete to inspect compaction and rebar placement. A 5000 <br /> PSI concrete mixture and curing agent will be used. This work is anticipated to be <br /> completed December 3 through December 7, 2007. The District will provide signage and <br /> flagmen to protect the public. Side walk areas will be plated during the non-construction <br /> times to protect the public against injury. The Lower Sacramento Road surface including <br /> the bridge lanes will be open and un-obscured to vehicle and pedestrian traffic. <br />