GENERAL NOTES: <br />must obtain an <br />Encroachment Permit from Caltrans and <br />the cities <br />1. One week prior to the start of work, the Contractor must furnish to the <br />Engineer a <br />schedule showing <br />proposed street closures on each half—day basis. <br />No work will commence until this schedule is approved by the Engineer. <br />within the City's <br />juruisdiction. <br />Payment for this will be considered to be <br />2. All intersection radii within project limits must be sealed to lip of existing <br />curb and <br />gutter or edge of <br />pavement. <br />3. Surface preparation work must be as directed by the Engineer. Locations <br />and dimensions <br />of Pavement <br />Repair will be determined by the Engineer. Slurry <br />Seal must not begin until the HMA used in Pavement Repair has been in <br />place for <br />a minimum of 18 <br />hours. <br />4. The aggregate for Slurry Seal must be Type II. <br />5. The Contractor must perform street sweeping throughout the duration of the Slurry Seal operations of the project per the specifications. Full <br />compensation for sweeping operations must be considered as included in the contract unit price paid for Slurry Seal (Type II) item of work and no <br />separate payment will be made therefor. <br />6. The Contractor must perform Slurry Seal operations on streets where schools are situated on the weekend or when school is not in session unless <br />allowed by written approval from the Engineer. <br />7. The contractor must not begin Slurry Sealing a street after 1:00pm without the approval from the Engineer. <br />8. Areas in County right—of—way used by Contractor for staging and/or storage of materials will be approved by the Engineer. The areas utilized by the <br />Contractor for staging and/or storage area must be restored to their original condition. Any damages or unclean conditions to staging or storage areas <br />must be repaired at the Contractor's own expense. It will be the Contractor's responsibility to obtain permission from the property owner to stage <br />equipment or store materials on private property. The Contractor must provide a letter of release from the property owner of the areas utilized for <br />staging and/or storage of materials. <br />9. Placement of No Parking signs/barricades must be placed no less than 72 hours prior to work. <br />10. Existing highway and utility facilities must remain in place unless otherwise noted. <br />11. Existing trees, shrubs, fences, mailboxes and other frontage improvements must remain in place unless otherwise noted. <br />12. Existing drainage facilities must remain in place unless otherwise noted. The Contractor must conduct earthwork operations so as not to modify or <br />obstruct the existing drainage. <br />13. The Contractor will be responsible for adequately scheduling inspection and testing of all facilities constructed under this contract with a minimum 24 <br />hour notice to the County. All testing must conform to the Standard Specifications. All re—testing will be paid by the Contractor. <br />14. The Contractor <br />must obtain an <br />Encroachment Permit from Caltrans and <br />the cities <br />of <br />Stockton, <br />Manteca, <br />Ripon, <br />and Tracy for traffic control or any work <br />within the City's <br />juruisdiction. <br />Payment for this will be considered to be <br />included <br />in <br />the various <br />items of <br />work. <br />caution and carefully preserve <br />15. The Contractor must obtain all permits and licenses required for <br />the construction and completion of the project, and must perform all work in <br />accordance with the requirements <br />and conditions <br />of all permits <br />and approvals <br />applicable to the project. <br />16. Hand grinding of Asphalt Concrete <br />pavement will <br />be required at <br />locations where existing highway and utility facilities are within the Pavement Repair limits. <br />Payment for hand grinding will be <br />considered as <br />included in the <br />contract unit <br />price paid for Pavement Repair. <br />17. The Contractor must exercise due <br />caution and carefully preserve <br />survey bench <br />marks, control points, reference points and all survey stakes, and must <br />bear all expenses for replacement <br />and/or errors <br />caused by their <br />unnecessary <br />loss or disturbance. <br />z . <br />o <br />COUNTY OF SAN JOAQUIN No SCALE GENERAL NOTES <br />SLURRY SEAL LOCAL ROADS 2016-2017 <br />Sheet No. <br />2 of 9 <br />