2 <br />GENERAL NOTES <br />G1. ALL CIRCUITRY SHOWN ON THESE DOCUMENTS IS DONE PER THE "ROUNDHOUSE" <br />METHOD. FOR EVERY GROUP OF THREE (3) CONSECUTIVE CIRCUITS IN PHASE <br />ORDER, THERE IS A DEDICATED NEUTRAL. FOR EXAMPLE, A HOMERUN <br />COMPRISED OF CIRCUITS 1, 3 AND 5 CONTAINS FOUR (4) CONDUCTORS; <br />THREE (3) HOTS AND ONE (1) NEUTRAL. A HOMERUN COMPRISED OF NON– <br />CONSECUTIVE NUMBERS OUT OF PHASE ORDER. I.E. 1, 9 AND 11 OR 3, 5, <br />7 CONTAINS FIVE (5) CONDUCTORS; THREE (3) HOTS AND TWO (2) NEUTRALS. <br />GROUND CONDUCTORS TYPICALLY ARE NOT SHOWN AS PART OF THE WIRE <br />COUNT. <br />G2. INSTALL AND CONNECT AN INSULATED COPPER GROUNDING CONDUCTOR OF SIZE <br />SHOWN OR PER CODE IN ALL BRANCH CIRCUIT RUNS. <br />G3 FURNISH AND INSTALL ALL PANELBOARDS WITH CIRCUIT BREAKERS AS SHOWN <br />ON PANELBOARD SUMMARY SCHEDULES. <br />G4 REFER TO ELECTRICAL SPECIFICATIONS FOR THE FIXTURE SCHEDULE. <br />G5 REFER TO ELECTRICAL ONE LINE DIAGRAM AND FEEDER SCHEDULE FOR <br />THE SIZE OF CONDUITS AND CONDUCTORS BETWEEN MAJOR POWER <br />COMPONENTS OF THE ELECTRICAL SYSTEM. <br />G6 THE CONTRACTOR SHALL VISIT THE JOBSITE AND VERIFY ALL EXISTING <br />CONDITIONS BEFORE BIDDING AND SHALL INCLUDE IN THE BID THE <br />NECESSARY COSTS TO CONSTRUCT THIS PROJECT IN ACCORDANCE WITH THE <br />ELECTRICAL DRAWiNGS, SPECIFICATIONS AND ALL APPLICABLE CODES. <br />G7 ALL ELECTRICAL MATERIALS AND EQUIPMENT SHALL BE LISTED BY UNDER– <br />WRITERS LABORATORIES AND BEAR THEIR LABEL. <br />G8 NOTE THAT LOCATIONS SHOWN ON THE DRAWINGS FOR ELECTRICAL <br />DEVICES ARE APPROXIMATE AND THAT THE FINAL LOCATIONS ARE TO <br />BE COORDINATED IN THE FIELD WITH THE ARCHITECT. <br />G9 CONTRACTOR SHALL REMOVE ALL LEFT OVER CONDUIT, WIRE, SCRAPS, <br />ETC. AND LEAVE PREMISES CLEAN AND FREE OF TRASH OR DEBRIS <br />RESULTING FROM HIS WORK. <br />G10 CONTRACTOR SHALL REPORT TO THE ARCHITECT ANY OBSERVATIONS <br />OF CONDITIONS WHICH ARE DISCOVERED ON THE SITE WHICH WOULD <br />PREVENT 'THE CORRECT INSTALLATION OF THE ELECTRICAL SYSTEM. <br />G11 CIRCUIT NUMBERING SYSTEM FOR MULTI–POLE CIRCUIT BREAKERS SHALL BE <br />AS FOLLOWS: FOR TWO POLE CIRCUIT BREAKERS, THE CIRCUIT NUMBER <br />USED FOR IDENTIFICATION SHALL BE THE TOP POLE OF THE TWO POLE USED <br />(I.E. BREAKER INSTALLED AT POLE NUMBERS 8, 10 IS IDENTIFIED AS CIRCUIT <br />No. 8). FOR THREE POLE CIRCUIT BREAKERS, THE CIRCUIT NUMBER USED <br />FOR IDENTIFICATION WILL BE THE CENTER POLE OF THE THREE POLES USED <br />(I.E. BREAKER INSTALLED AT POLE NUMBERS 8, 10, 12 IS IDENTIFIED AS <br />CIRCUIT No. 10). <br />SITE NOTES <br />S1. DRAWINGS ARE DIAGRAMMATIC AND INDICATE GENERAL ARRANGEMENT OF <br />SYSTEMS AND WORK. FOLLOW DRAWINGS IN LAYING OUT WORK AND CHECK <br />DRAWINGS OF OTHER TRADES TO VERIFY SPACE CONDITIONS. <br />S2. REFER TO CIVIL DRAWINGS FOR LOCATIONS OF LIGHTING FIXTURES ON HARD <br />SURFACES. REFER TO LANDSCAPE DRAWINGS FOR LOCATIONS OF LIGHTING <br />FIXTURES IN EARTH AND LANDSCAPE AREAS. <br />S3. PULLBOXES ARE TO BE GENERALLY LOCATED AS FOLLOWS: <br />1. BEHIND SIDEWALKS: LENGTHWISE PARALLEL TO SIDEWALK WITH EDGE OF <br />PULLBOX 3" FROM EDGE OF SIDEWALK. SHERE PULLBOX IS ADJACENT <br />TO POLEBASE, INSTALL ON SIDE OF POLE OPPOSITE SIDEWALK. <br />2. IN MEDIAN STRIPS: CENTERED WITH LENGTH PARALLEL TO LENGTH <br />OF MEDIAN. <br />3. IN BERM AREAS: LENGTHWISE PARALLEL TO CURB WITH EDGE OF PULLBOX <br />3" FROM BACK EDGE OF CURB. <br />S4. POWER PEDESTALS ARE TO BE INSTALLED GENERALLY AT LOCATIONS SHOWN. <br />COORDINATE WITH ARCHITECT PRIOR TO INSTALLATION. <br />S5. SIZE PULLBOXES AS SHOWN ON DRAWINGS. OBTAIN <br />ARCHITECTS APPROVAL OF ANY PULLBOX(ES) ADDED TO FACILITATE THE <br />INSTALLATION OF CONDUITS SHOWN ON THE PLANS. <br />S6. ALL WORK SHALL BE LOCATED IN PUBLIC UTILITY EASEMENT. EQUIPMENT <br />AND DUCT BANKS IN GENERAL ARE SHOWN LOCATED IN EASEMENTS. <br />CONTRACTOR SHALL REFER TO EASEMENT DRAWINGS DURING CONSTRUCTION <br />TO MAINTAIN ALL EQUIPMENT AND DUCTS WITHIN EASEMENTS. <br />S7. COORDINATE LOCATIONS OF ALL SITE PULLBOXES, TRANSFORMER PADS <br />AND TRENCHING WITH LANDSCAPE ARCHITECT PRIOR TO INSTALLATION. <br />S8. REFER TO THE CIVIL DRAWINGS FOR BERM INFORMATION AND LANDSCAPE <br />DRAWINGS FOR LOCATION AND TYPE OF TREES. <br />S9. REFER TO CIVIL AND LANDSCAPE DRAWINGS FOR EXACT LOCATIONS OF <br />ILLUMINATED SIGNS. <br />CONDUIT NOTES <br />C1. CONDUIT ROUTING (WHERE SHOWN) IS ESSENTIALLY DIAGRAMMATIC. <br />CONTRACTOR SHALL LAYOUT RUNS TO SUIT FIELD CONDITIONS AND THE <br />COORDINATION REQUIREMENTS OF UTILITIES AND OTHER TRADES. <br />C2. INSTALL A POLYETHYLENE PULLING ROPE IN ALL EMPTY CONDUITS. <br />NUMBERED NOTES <br />1� PROVIDE BASE ONLY FOR FIXTURE TYPE F1A AT THIS LOCATION. PROVIDE <br />COVER OVER BOLTS FOR PROTECTION . INCLUDE ALL CONDUITS INTO AND <br />OUT OF BASE. FURNISH ONE FIXTURE TYPE F1A TO OWNER FOR HIS <br />INSTALLATION AT A FUTURE DATE. <br />0 AT THIS LOCATION PROVIDE A TEMPORARY 15' HIGH WOODEN LIGHT POLE <br />WITH ONE FIXTURE TYPE F6 MOUNTED AT THE TOP. REFER TO CIVIL <br />DRAWIGS FOR DETAIL OF WOODEN POLE AND FEED. MAKE LIQUIDTIGHT CONDUIT <br />CONNECTION TO FIXTURE. <br />0 STUB 2" CONDUIT 12" BEYOND PERIMETER OF POLE BASE. PROVIDE <br />CONDUIT MARKER PER DRAWING E7.1, DETAIL A. <br />® PROVIDE CONDUIT STUB MARKER PER DRAWING E-7.1, DETAIL A. <br />0 PROVIDE 2" CONDUIT BETWEEN POINTS SHOWN. TERMINATE 12" 13EYOND <br />SIDEWALK WHERE APPLICABLE AND 24" BEYOND CURB WHERE NO SIDEWALK <br />EXISTS. PROVIDE CONDUIT STUB MARKER PER DRAWING E7.1, DETAIL <br />A AT EACH END. <br />© PHASE 1A.3 SIDE SHALL BE DONE FIRST PER CIVIL PHASING DRAWING. <br />STUB CONDUIT TO EDGE OF PHASE 1A.3 WORK, CAP AND INSTALL <br />CONDUIT STUB MARKER. WHEN PRASE 1A.3 IS COMPLETE, PERFORM THE <br />WORK IN PHASE 1A.4-5 BY EXTENDING THE CONDUIT AS SHOWN AND <br />INSTALLING AND CONNECTION WIRING. <br />0 STUB 2-2" MT SIGNAL AND 1-2" MT EMERGENCY CONDUITS INTO MEDIAN <br />STRIP AND STUB UP 6" VERTICALLY. COORDINATE EXACT LOCATION OF <br />STUBUPS WITH ARCHITECT PRIOR TO INSTALLING. <br />0 REFER TO SECTION 165,35 FOR DETAILS CONCERNING SURFACE FLOODLIGHTS <br />AND DIRECTIONAL LANDING LIGHTS. LOCATE LIGHTS AS SHOWN ON <br />DRAWING C1.52.INSTALL PER MANUFACTURERS RECOMMENDATIONS AND <br />CIVIL DRAWING DETAILS. <br />SYSTEMS AND DEVICES DENOTED BY THIS NUMBERED NOTE SHALL <br />BE INSTALLED DURING PHASE 1A.3. CARE SHALL BE TAKEN DURING THE <br />CONSTRUCTION IN SUBSEQUENT PHASES TO PROTECT THE SYSTEMS <br />AND DEVICES FROM DAMAGE AND TO INSURE THAT THEY REMAIN OPERATIONAL. <br />0 STUB CONDUITS TO THE EDGE OF THE BORDER BETWEEN PHASE 1A AND 113 <br />AND CAP. PROVIDE CONDUIT STUB MARKER PER DRAWING E7.1, <br />DETAIL A. <br />01 TEMPORARY CONNECTION BETWEEN NORMAL AND EMERGENCY PULLBOXES FOR <br />NORMAL FEED TO EMERGENCY FIXTURES. CIRCUITS WILL BE SPLIT AT <br />END OF PHASE 1 B. <br />0 INSTALL FIXTURE TYPE F5 AT LOCATION WHICH CORRESPONDS TO LOCATION <br />OF TEMPORARY SIGN. INSTALL 8' FROM SIGN AT CENTERPOINT OF SIGN. <br />COORDINATE WITH CIVIL DRAWINGS. AT SUCH TIME AS PERMANENT <br />INTERNALLY LIGHTED SIGN IS INSTALLED, MAKE CONNECTION TO PERMANENT <br />SIGN, DISCONNECT TEMPORARY SIGN LIGHT, REMOVE LIGHT AND TURN <br />OVER TO OWNER. <br />0 INSTALL FIXTURE TYPE F5 AT LOCATION WHICH CORRESPONDS TO LOCATION <br />OF TEMPORARY SIGN. INSTALL 8' FROM SIGN AT CENTERPOINT OF SIGN. <br />COORDINATE WITH CIVIL DRAWINGS. <br />LOCATION OF TEMPORARY ELECTRIC DISTRIBUTION BOARD PROVIDED <br />BY CIVIL DRAWINGS. SEE DETAIL 16, DRAWING C1.04. ADJACENT TO THAT <br />EQUIPMENT, PROVIDE A WP, PADMOUNT 30KVA 240V, 10,2W TO 277/480V <br />10, 3W TRANSFORMER. <br />3 APPROXIMATE LOCATION OF OWNER FURNISHED PANELBOARD TOPD. MAKE <br />CONNECTIONS TO TOPD AS REQUIRED BY SITE CIRCUITING. <br />0 PROVIDE BASE AND CONDUIT STUBS FOR ONE FIXTURE TYPE F3 <br />AT THIS LOCATION. <br />SYMBOLS <br />---- <br />CONDUIT RUN CONCEALED IN SLAB, UNDER SLAB OR UNDERGROUND. <br />— <br />CROSSMARKS ON BRANCH CIRCUIT CONDUIT RUNS INDICATE THE QUANTITY <br />OF CONDUCTORS AS FOLLOWS: <br />1 . NO CROSSMARKS INDICATES TWO #8 & 1#8 GND CONDUCTORS, UON. <br />2. THREE OR MORE CROSSMARKS INDICATES THE QUANTITY OF #8 AWG <br />CONDUCTORS, UON. INCLUDE 1#8 GND IN ALL RUNS. THIS CONDUCTOR <br />IS NOT SHOWN. <br />NO SUBSCRIPT INDICATES NORMAL SYSTEM FEEDER. 'E' SUBSCRIPT INDICATES <br />EMERGENCY SYSTEM FEEDER. <br />S — <br />CROSSMARKS ON BRANCH CIRCUIT CONDUIT RUNS INDICATE THE QUANTITY <br />OF CONDUCTORS AS FOLLOWS: <br />D• <br />H.I.D. CUTOFF LIGHTING FIXTURE, POLE MOUNTED, SINGLE HEAD. <br />DOE] <br />H.I.D. CUTOFF LIGHTING FIXTURE, POLE MOUNTED, DOUBLE HEAD. <br />.O <br />BOLLARD OR POLE MOUNTED FIXTURE. <br />J[] <br />IN GRADE PULLBOX, SIZE AS SHOWN ON THE DRAWINGS. N INDICATES <br />NORMAL SYSTEM, E INDICATES EMERGENCY SYSTEM, S INDICATES <br />SECURITY SYSTEM. <br />10 <br />NUMBERED NOTE: <br />APPLIES TO ALL DRAWINGS. <br />Stone <br />Marraccini <br />Patterson <br />Architecture <br />Planning <br />Interior Architecture <br />One Market Plaza <br />Spear Street Tower <br />Suite 400 <br />San Francisco <br />CA 94105 <br />415 227-0100 <br />Architect,AIA <br />Tech. Checked Tech. <br />Coord. Arch. <br />RUTHERFORD & CHEKENE <br />303 Second St. Suite 800 N. <br />San Francisco, CA 94107 <br />Structural Engineer <br />GUTTMAN & MacRITCHIE <br />631 Howard Street, Suite 500 <br />San Francisco, CA 94105 <br />Mechanical Engineer <br />THE ENGINEERING ENTERPRISE <br />1305 Marina Village Parkway <br />Alameda, CA 94501 <br />Electrical Engineer <br />Approvals <br />Revisions <br />No. <br />SAN JOAQUIN <br />GENERAL HOSPITAL <br />REPLACEMENT PROJECT <br />PHASE 1A <br />ELECTRICAL NOTES, <br />SYMBOLS AND <br />DETAILS <br />Scale: As Noted <br />Project No. <br />53000.09 <br />Date <br />23 MAR 1992 <br />Date <br />Drawing No. <br />E 1.0 <br />