SPECIFICATIONS <br /> 1.1 UNDERGROUND TANKS <br /> A. RESPONSIBILITY: <br /> I. The Contractor accepts full responsibility for proper handling and installation of the fiberglass <br /> reinforced plastic (FRP) or composite underground tanks and FRP piping, and shall ensure that <br /> good workmanship, practices and construction procedures are followed during the handling and <br /> installation of the tanks and piping. <br /> 2. The Contractor Is responsible for Inspecting the tanks for damage upon receipt at the Job site. <br /> Any visible damage Is to be noted on the delivery receipt. <br /> 3, The presence of the Chevron Repr on-site does not relieve the Contractor of the responsibility <br /> for proper lank handling, Installation and safety measures. <br /> FUEL DISPENSER. 66 OR 67 1.2 REMOVAL OF EXISTING TANKS AND PIPING SYSTEMS <br /> SEE@A. RESPONSIBILITY: Contractor will furnish permits, labor and proper equipment, except as noted, to <br /> F-6 remove existing tanks and lines per the following procedure: <br /> 1. Contractor, as part of the contract, will execute and comply with the Componys "Addendum <br /> Q Tank Disposal Certification Agreement". <br /> Q 2. All tanks and piping shall be removed and disposed of in accordance with the Addendum Tank <br /> Q Disposal Certification Agreement and applicable state and local regulations. Removal of tanks <br /> and Imes shall comply wlih API Hseem mend ed Practice 1604, Removal and Disposal of Used <br /> Underground Storage Tanks - December 1987 and March 1989 supplement. <br /> 3, Contractor shall comply with current NFPA and local regulations. <br /> U 4. Chevron Is responsible for removal of all reusable product from the tanks. Product will be <br /> 5 returned to terminal or other company facility. <br /> Q VR 8, REMOVAL PROCEDURE: <br /> REDUCE VAPOR TO 1. Excavate to the top of each tank. Care must be taken to prevent breaking product piping. Prior <br /> 2'0 LINE to slarting excavation, the contractor shall ensure power is shut off to any circuit, whose <br /> (TYP.) 20 Q conduit may cross the excavation. <br /> U RUN PRODUCT PIPING a. Suction System: Open check valve, pull poppet and drain product from line into tank. Do not <br /> 5 AND ELECTRICAL replace poppet. Reinstall cover on valve. <br /> Vp CONDUIT INTO r' b, Pressure System: "Break" pipe at union at remote pump. Orcin product Into tank or separate <br /> OPPOSITE SIDES OF U container. <br /> DISPENSERS (TYP.) 2. Avoid spills. product to drain into soil. Contractor may be held liable If soil <br /> 2"0 PRODUCT IN (SEE PIPING PLAN) contamination occurs duringtank and line removal. <br /> f 3"0 SEC. COIN. PIPE 18 19 3. Flush all product, vent and vapor return line back In lank or separate container(s). (Flushing in <br /> 3"0 V.R. Q S U separate containers can be dumped into product tanks for storage.) Flush each line with a <br /> minimum of 70 gallons o1 water. <br /> VR 4. Open all openings and flush inside of each tank with a minimum of 200 gallons of water using <br /> 2"0 PRODUCT IN REDUCE VAPOR TO high pressure spray equipment with wand to "wash dawn" the sides and bottom of the tank. <br /> 3"0 SEC. GON. PIPE 18 79 2'0 LINE 5. Chevron will arrange for a vacuum truck to collect all recovered product (liquid and sludge). <br /> (TYP.) 20 O Vacuum truck Is to return recovered" product to "slop" of Chevron facility or approved treating <br /> 5 U facility with approved oil/water separator system. <br /> 6. The tank must be free of flammable vapors prior to removal. Remove flammable vapors as <br /> P/V VALVE AS __-_ yR prescribed by the presiding fire deportment and tank manufacturers requirements. <br /> REQUIRED BY �I '0 PRODUCT IN 7. After tank venting, the vapor space sholl be tested by placing the combustible gas Indictor probe <br /> 2 <br /> LOCAL CODE Q Q into the fill opening with the drop lube removed. Reading should be taken at the bottom, middle <br /> 3"0 SEC. CON. PIPE 1B 19 and upper portions of the tank. The tank atmosphere must be 20% or less of the lower <br /> U flammable limit prior to removal. Refer to the probe manufacturer's instructions for testing In low <br /> 5 oxygen conditions. <br /> B. Prior to removal, all tank openings should be plugged. One plug should have a 1/8' vent hole to <br /> i F-4 6 Q Q VR prevent excessive pressure buildup. This vent hole must face upward at all limes. <br /> i REDUCE VAPOR TO 9. Plug any corrosion caused holes using screwed boiler plugs. Chevron Rep will inspect the <br /> i <br /> VENT RISERS, F-4 2"0 LINE removed tanks, then release the tanks /or shipment. <br /> SEE SITE PLAN FOR ACTUAL LOCATION. (IYio 20 f,. POST-REMOVAL PROCEDURE. <br /> UP TO VENT RISER. (MIN. SLOPE 1/4"/FT.). <br /> INSTALL MAXIMUM SLOPE FROM TANK 5 U I. All U.L. labels shall be removed and given to the Chevron Rep. <br /> _ VR must <br /> All (oohs must be properly labeled prior to transportation from the site. Transport of the tanks <br /> SEE@ SLOPE VAPOR RETURN LINE 3"0 V.R. 2"0 PRODUCT IN must be done in accordance with all state and local regulations. <br /> F-4 0 SEC. CON. PIPE 18 19 1 Follow any state or local regulations regarding soil samples or inspection of tank hale and/or <br /> 1/4' PER FT. MIN. DOWN TO 2'0 PRODUCT IN 3" <br /> REGULAR UNLEADED TANK.- 3"0 SEC. CON. PIPE gg tanks. When free product Is found during any phase of the removal of underground tonk(s) or <br /> 3"0 V.R. piping system(s), Immedlalely notify the Chevron Rep. <br /> o NOTE. <br /> 7 p `�.,�� FIBERGLASS SUMP <br /> i SHOWN IN SECTION NOTES <br /> F-5 S I, > FOR CLARITY. <br /> i CONTAINMENT SUMP I. TYPICAL PIPING LAYOUT SHOWN FOR MULTI-PRODUCT DISPENSERS. SEE PLANS FOR <br /> (TYP. 2) SPECIFIC DISPENSER TYPE AND CONFIGURATION FOR THIS SITE. <br /> SEE @ 2. ALL PRODUCT LINES ARE TO BE SECONDARILY CONTAINED. <br /> 4 <br /> i F-4 F 5 SLOPE PRODUCT LINES 3. EVERY TANK CONTAINMENT SUMP AND DISPENSER CONTAINMENT SUMP SHALL CONTAIN <br /> 1/4" PER FOOT MINIMUM <br /> A LIQUID SENSING PROBE. <br /> FROM DISPENSERS TO TANK (TYP.) <br /> 2"0 VENT 4. CAULK THE BOTTOM OF THE DISPENSERS TO INSURE WATER PGH TNESS. <br /> 5. PERPENDICULAR PENETRATIONS OF THE CONTAINMENT SUMPS ARE PREFERRED. <br /> 20' IS TIE MAXIMUM ALLOWABLE PENETRATION ANGLE. <br /> 2"0 V.R. <br /> 3"0 V.R. 2"0 VENT <br /> ' B. SPARE ELECTRICAL CONDUITS MUST BE SEALED. <br /> 1. SEE SHEET E-1 FOR ELECTRICAL CONDUIT LAYOUT, <br /> 3"x3 x2 F,R.P. TEE \ 8. OBTAIN WRITTEN APPROVAL FROM CHEVRON FOR LESS THAN 1/4' PER FOOT <br /> SLOPE ON PRODUCT, VAPOR AND VENT LINES. <br /> 3'0 R. — 9. TANK RISERS AND DISPENSER PIPING MUST BE ADDRESSED AS FOLLOWS FOR TANKS <br /> 3 V.R. CONTAINING GASOLINE: <br /> 0 ANNULAR SPACE RISER MUST BE SCHEDULE 40 GALVANIZED PIPE THAT IS PRIMED <br /> AND WRAPPED. <br /> • FILL, VAPOR AND AUTOMATIC TANK RISER MUST BE SCHEDULE 40 GALVANIZED PIPE. <br /> SEE SITE PLAN FOR EACH RISER MUST BE PRIMED AND WRAPPED IF BACKFILL 15 TOUCHING THE RISER. <br /> UPRE EXACT INSTALLATION LOCATION <br /> • TURBINE RISER MUST BE SCHEDULE 40 BLACK IRON PIPE. <br /> UNC E OF STORAGE TANKS. • ALL STEEL DISPENSER PIPING AND FITTINGS MUST BE SCHEDULE 40 BLACK IRON PIPE <br /> EADED AND PAINTED BLACK, <br /> REGU 10. FOR MANIFOLDED UNLEAD TANKS USING RED JACKET SUBMERSIBLE TURBINE PUMPS <br /> INSTALL A "MORRISON" CHECK <br /> VALVE µ530-25T OR APPROVED EQUAL AT EACH <br /> UNLEADED UNLEADED <br /> UNDERGROUNDTANK AND PIPING ISOMETRIC 11. USE 3'0 VAPOR RECOVERY PIPING ALL THE WAY BACK TO REGULAR UNLEADED TANK. <br /> SCALE: NONE 12. SUPREME SIDE OF DISPENSERS MUST ALWAYS BE ON THE LEFT. <br /> SLOPE 3'0 VAPOR RETURN UNE <br /> 1/4' PER FT. MIN, DOWN TO <br /> LAST REGULAR TANK. <br /> .J <br /> Chevron U.S.A. Inc. ("Chevron") owns the copyright rights to the design of the herein described fueling ; <br /> system as embodied in any tangible or electronic medium of expression Including all building O <br /> designs, architectural plans and drawings. The copyrighted material includes the overall form as well as <br /> the arrangement and composition of spaces and elements in the design, but does not include individual <br /> standard lectures. Anyone who wishes to copy, distribute or sell this drawing or any derivative works CLCL <br /> based hereon must have the prior written consent of Chevron, except for copies made for the sole <br /> purpose of preparing construction drawings for Chevron branded facilities and all such copies shall be Q <br /> 2'0 V.R, returned to Chevron upon request. '^ <br /> ©1995 Chevron U.S A. Inc. All rights reserved. SILL <br /> The drawings, calculations, and any specific reference to equipment, materials or components, W <br /> if included herein, are generic and not designed for site specific applications. Chevron does not warrant t� <br /> 2"0 V.R. or guaranty the accuracy, completeness, merchantability, Intended use or applicability of such drawings, <br /> calculations, and any referenced equipment, materials or components, to the requirements or <br /> needs of your site or local area. Consult a registered architect or professional engineer to determine <br /> any site specific design, applicability, accessibility, building code, municipal requirements and any and <br /> all applicable federal, slate and local statutes, rules and regulations which may affect your site. <br /> Chevron does not provide these services. <br /> 3"0 V.R. <br /> SUP TRIC, ur�aGROUND STORAGE TANG <br /> UN�EADEp SYST <br /> AND HARD PFM (BLEND B() <br /> REGULAR <br /> Chevron 9-6171 <br /> UNLEADED Marketing 6633 PACIFIC AVENUE <br /> RN`egoRp STOCKTON, CALIFORNIA <br /> ROVIIIIII SCALE 1/4'-T-O' DAM20NOV97 <br /> MANIFOLDED REGULAR UNLEADED TANKS DR CR APP. <br /> SCALE: NONE �r <br /> �I <br />