. S ECOR - • _. <br /> Work Plan for Monitoring Well Installation <br /> July 31, 2007 <br /> Former ARCO Service Station No. 4932 <br /> Stockton, California <br /> Page 5 <br /> Wells DMW-2, DMW-3, and EW-2 are located off-site north across E. Harding Way from the <br /> site. <br /> In August 2002, SECOR submitted a Problem Assessment Report (PAR), which evaluated <br /> various remedial alternatives for the site. SECOR recommended the installation of a GWE and <br /> SVE system. The recommendation included the installation of five additional GWE (EW-3 <br /> through EW-7) wells and one SVE well. SJCEHD approved the remedial recommendations in <br /> their letter dated November 7, 2002. Off-site extraction wells EW-2, EW-3, EWA EW-5, and <br /> EW-7 were pumped on a weekly basis, and the water was treated through the on-site GWE <br /> system, until the installation of the off-site ozone sparge system was completed during the <br /> second quarter 2005. The GWE portion of the DPE system is comprised of submersible pumps <br /> installed in wells EW-1 and EW-6 and "slurp" tubes installed in wells MW-4 and EW-7, which are <br /> connected to an air stripper and three 2,000 Ib-granular activated carbon vessels. Extracted <br /> groundwater is treated prior to discharge to a City of Stockton sanitary sewer line. <br /> From March 7 to 10, 2005, SECOR supervised the drilling of six soil borings and installation of <br /> six ozone sparging wells using a limited access drilling rig equipped with 8-inch-diameter <br /> hollow-stem augers. Wells S-1 through S-6 were drilled to a depth of approximately 40 feet bgs <br /> to accommodate ozone sparge wells. Soil samples were collected in the bottom five feet of <br /> each boring during well installation activities for logging purposes only. Ozone sparge wells OS- <br /> 1 through OS-6 were constructed of/< inch diameter schedule 80 PVC blank casing and a 3- <br /> foot long sparging micropore screen. The sparge tips were installed at an approximate depth of <br /> 40 feet bgs. A sand filter pack was placed within the annulus of the well from the bottom of the <br /> boring to approximately two to four feet above the top of the well screen. The annulus of the <br /> well was sealed with two feet of bentonite on top of the sand, and portland cement/bentonite <br /> slurry to the surface. An 8-inch-diameter, traffic-rated, watertight well box was installed. <br /> Remediation system construction began on May 2, 2005 and was completed on May 19, 2005. <br /> Ozone system installation included the placement of injection tubing (approximately '/2-inch <br /> diameter), doubly-contained in PVC tubing, connecting each ozone sparge well to a six-point <br /> ozone sparge panel located near the west end of the Taco Bell building. The panel was <br /> plumbed to a six-point injection within the ozone sparging unit, allowing rotation of the injection <br /> lines between the six ozone sparge points. The ozone injection system consists of Calcon <br /> model HiPro500 that produces 0.5 pounds per day of ozone. The ozone unit is equipped with a <br /> compressor rated to deliver four standard cubic feet per minute (scf/m) at 40 pounds per square <br /> inch (psi). <br /> On September 2005, the remediation system was shutdown due to electrical damage. The <br /> remediation system remained shutdown between September 2005 and June 2006. On August <br /> 2006, the remediation system was restarted and a source test was performed for the SJCEHD. <br /> The remediation system has been operational since August 2006. <br /> GEOLOGY AND HYDROGEOLOGY <br /> Lithology beneath the site generally consists of fine-grained silts and clay from ground surface <br /> to approximately 20 feet bgs, and from 30 to approximately 60 feet bgs. Silty sands and sands <br /> are generally present at the intervals of 20 to 30 feet bgs, and 60 to 85 feet bgs. <br /> Depth-to-groundwater has varied from approximately 25.83 feet bgs in MW-3 (5/2001) to 36.86 <br /> feet bgs in EW-7 (1/2004) since the installation of monitoring wells began in 2000. Depth-to- <br /> groundwater encountered during drilling has been approximately 30 feet bgs indicating that the <br /> 4932 WP for MW Installation 2007.doc SECOR International Incorporated <br />