TANK AND PIPING INSTALLATION SCOPE OF WORK: CLIENT:
<br /> GENERAL: TOP OF TANK ELEVATION: ��
<br /> SCOPE OF WORK: UNLESS SPECIFIED OTHERWISE ON THESE DRAWINGS, THE GENERAL CONTRACTOR SHALL FURNISH ALL WORK AND MATERIALS TO CONTRACTOR TO CALCULATE TOP OF TANK ELEVATION. START WITH 18" MINIMUM DEPTH OF VAPOR RECOVERY LINE AT THE FARTHEST DISPENSER / 1
<br /> COMPLETE THE INSTALLATION OF THE SYSTEMS AND EQUIPMENT SHOWN IN THESE DRAWINGS AND AS REQUIRED BY PROJECT DOCUMENTS PROVIDED AND SLOPE 1/4" PER FOOT MAXIMUM TO 1/8" PER FOOT MINIMUM. ADD 12" AT THE TANK. ADD 13" (FOR 3" PIPE) OR 8" (FOR 2") FOR A tit NOT USED: ;
<br /> TO THE CONTRACTOR. CHANGE IN PIPING DIRECTION OTHER THAN 90 OR 45 DEGREES. SET TANKS 6" DEEPER THAN CALCULATED AS PRECAUTION. IN NO EVENT SHALL
<br /> THE TANK BE BURIED LESS THAN 4'-0" BELOW FINISHED GRADE OR DEEPER THAN 7'-0" BELOW FINISHED GRADE, SEE MANUFACTURERS
<br /> WHERE THESE DRAWINGS DIFFER FROM LOCAL REGULATIONS, LOCAL REGULATIONS WILL SUPERSEDE THESE DRAWINGS IF THEY ARE MORE STRINGENT. INSTALLATION INSTRUCTIONS FOR MINIMAL TANK BURY WHEN DEADMEN ANCHORING IS NOT PROVIDED. ANY VARIATIONS IN SLOPE FROM 1/4" PER
<br /> NOTE: FOOT SHALL BE REPORTED TO OWNER'S ENGINEER,
<br /> THESE GUIDELINES APPLY ONLY TO UNDERGROUND STORAGE TANKS AND PRODUCT PIPING. REFER TO BALANCE OF SITE SPECIFIC DOCUMENTS/ TANK EXCAVATION:
<br /> DRAWINGS FOR SPECIFICATIONS REGARDING CONCRETE/ASPHALT INSTALLATION, ELECTRICAL REQUIREMENTS, AND SANITARY & STORM SEWERS CONTRACTOR TO EXCAVATE TANK HOLE. CONTRACTOR SHALL ADHERE TO O.S.H.A. STANDARDS ON EXCAVATIONS. CONTRACTOR MAY SELECT ANY OF
<br /> INSTALLATION. THE RECOMMENDED PRACTICES FOR TANK EXCAVATION AND MUST PROVIDE ALL NECESSARY PROTECTIVE BARRICADES.
<br /> *** WHERE MULTIPLE VERSIONS OF THE SAME SHEET EXIST, INSERT *** SLOPE SIDES OF TANK HOLE OR USE SHORING FOR ALL TANK EXCAVATIONS IN ACCORDANCE WITH OSHA 1926 SUBPART P, OSHA
<br /> THE SHEET APPROPRIATE FOR THE SPECIFIC STATION LAYOUT. STANDARDS — EXCAVATIONS; FINAL RULE OCTOBER 1, 1989. WHEN ENGINEERED SHORING IS REQUIRED DUE TO SITE CONDITIONS AN
<br /> ENGINEERED SHORING PLAN UTILIZING INTERLOCKING STEEL SHEET PILING SHALL BE PROVIDED AND SHALL INCLUDE SUPPORTING
<br /> ARCHITECTURAL AND CIVIL DRAWINGS SHALL TAKE PRECEDENCE FOR REFERENCING ALL DIMENSIONS, PROPERTY LINES, ELEVATIONS AND ENGINEERING CALCULATIONS BY A STATE CERTIFIED ENGINEER AND SHALL BE THE RESPONSIBILITY OF THE INSTALLING CONTRACTOR.
<br /> EQUIPMENT LOCATIONS
<br /> GENERAL CONTRACTOR SHALL OBTAIN NECESSARY PERMIT FROM APPLICABLE AGENCIES FOR EXCAVATIONS OF TRENCHES 5'-0" OR MORE
<br /> ALL DIMENSIONS AND CONDITIONS SHALL BE CHECKED AND VERIFIED IN THE FIELD BEFORE STARTING ANY WORK. ANY DISCREPANCY SHALL IN DEPTH INTO WHICH A PERSON IS REQUIRED TO DESCEND. (8) PRODUCT PIPING INSTALLATION:
<br /> BE CALLED TO THE ATTENTION OF THE OWNERS ENGINEER FOR HIS DECISION BEFORE PROCEEDING WITH THE WORK. TANK EXCAVATIONS SHALL BE THE MINIMUM SIZE REQUIRED TO PROVIDE FOR BEDDING AND CLEARANCES INDICATED IN THESE DRAWINGS. TANK
<br /> ALL REQUESTS TO ADD, DELETE, OR SUBSTITUTE MATERIAL AND EQUIPMENT SHOWN ON THESE DRAWINGS MUST BE REVIEWED AND APPROVED BY BURIAL DEPTH FIELD DETERMINED TO PROVIDE FOR 1/4" (1/8" PER FOOT MIN.) PER FOOT FOR STAGE li VAPOR RECOVERY PIPING & 1/8" STANDARD: CONTRACTOR TO INSTALL DOUBLE WALL FIBERGLASS PRODUCT PIPING, CONNECTORS, VALVES AND FITTINGS IN TANK AND DISPENSER
<br /> THE OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER, IN CHARGE OF THE PROJECT. ALL CHANGES MUST BE REVIEWED WITH MINIMUM PER FOOT FOR PRODUCT PIPING SLOPE BACK FROM DISPENSERS TO TANK. SUMPS AS SHOWN ON SITE SPECIFIC DETAIL DRAWINGS TO SUPPLY DISPENSERS. PRODUCT PIPING TO BE SMITH FIBERCAST RED THREAD IIA, 2"
<br /> THE MARKETING FUELS MANAGER. TANK STABILITY BUOYANCY CALCULATIONS: INSIDE 3" DIAMETER AS INDICATED ON SITE SPECIFIC FUELING PLAN, ALL PIPING AND FITTINGS SHALL BE UL-971 LISTED IN COMPLIANCE WITH THE ARCO
<br /> THE CONTRACTOR IS REQUIRED TO FURNISH AS-BUILT DRAWINGS TO LOCATE TANKS AND PIPING AS INSTALLED AFTER THE COMPLETION OF THE TANK STABILITY SHALL BE RE-CHECKED AGAINST FLOATATION BY INSTALLING CONTRACTOR. SEE BUOYANCY CALCULATIONS ON TANK DETAILING SHEETS. JULY 2005 PERFORMANCE STANDARDSAND SHALL BE COMPATIBLE WITH ETHANOLINCLUDING BUT NOT LIMITED TO E85 (85% ETHANOL 15%
<br /> PROJECT. , ,TANK ANCHORING: GASOLINE). PRODUCTS LINES TO BE EQUIPPED 3 GPH PRESSURE LINE LEAK DETECTORSPLLD ON TURBINES AND WITH LIQUID LEAK MONITORING
<br /> ( ) BP WEST COAST PRODUCTS,LLC
<br /> (1 ) TANK INSTALLATION: CONTRACTOR TO INSTALL MANUFACTURER SUPPLIED TANK HOLD DOWN STRAPS & ANCHORS WHEN REQUIRED DUE TO HIGH WATER TABLE, LOCAL SENSORS LOCATED IN TURBINE PIPING SUMPS ATTACHED TO TANKS WIRED FOR TURBINE SHUT DOWN. PRODUCT PIPING IN TURBINE SUMPS,
<br /> STANDARD: TR T TLS—350 OR SPECIFIED BY SITE ENGINEER/DESIGNER AND/OR OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER. WHEN PRODUCT PIPING CROSS CONNECTION MANIFOLDS BETWEEN SUMPS AND SIPHON PIPING PENETRATIONS ARE TO ENTER THE SAME SIDE OF THE SUMP
<br /> ND RD. CON ACTOR 0 INSTALL DOUBLE WALL FIBERGLASS TANKS WITH COMPLETE "VEEDER ROOT" TLS 350 TANK AND PIPING MONITORING AND REQUIRED, THE ANCHORING SYSTEM SHALL BE IN COMPLIANCE WITH AUTHORITY HAVING JURISDICTION. ANCHOR & STRAPS TO BE INSTALLED ACCORDING TO IF POSSIBLE. IF PRODUCT PENETRATION ENTERS ON BOTH SIDES OF SUMP DUE TO FIELD CONDITIONS, THEN DUAL SENSORS AT TURBINE SUMP MAY
<br /> ALARM SYSTEM. TANKS TO BE SET MIN. 48' BELOW FINISH GRADE. SEE SITE SPECIFIC INSTALLATION DETAILS FOR TANK SIZES AND LOCATIONS. MANUFACTURER'S INSTRUCTIONS. BE REQUIRED TO BE INSTALLED BY LOCAL REGULATIONS. IF THE BP PROJECT MANAGER DETERMINES THAT THE ALL THE PIPING ENTRIES NOTEDu /�
<br /> * ALTERNATE ANCHORING BY USE OF A CONCRETE ANCHORING SLAB IS PERMITTED. WHEN GROUNDWATER LEVEL IS ANTICIPATED TO BE ABOVE COULD HAVE BEEN MADE TO THE SAME SIDE OF THE SUMP, THEN ANY COSTS ASSOCIATED WITH EXTRA SENSORS SHALL BE BORNE BY THE ��H A
<br /> ARCOBRANDED VARIANT: DUAL FILLS AND STAGE I VAPOR RETURNS TO BE INSTALLED ON 25,000 GALLON TANK ONLY. HIN 5 FT. OF GRADE CONTRACTOR SHALL NOTIFY OWNER'S REPRESENTATIVE FOR DIRECTION ON ANCHORING METHOD TO BE USED INSTALLING CONTRACTOR. PIPING TO BE INSTALLED WITH A SLOPE OF 1/8 PER FOOT MINIMUM TO TANKS UNLESS APPROVED BY OWNER. ` V�
<br /> EADMAN OR ANCHORING SLAB) AND SUCH SHALL BE INSTALLED ACCORDING TO MANUFACTURER'S RECOMMENDATION. CONTRACTOR TO INSTALL TRACER TAPE WITH PRODUCT PIPING PER TRENCHING DETAILS. PENETRATIONS INTO ALL SUMPS SHALL BE MADE WITH
<br /> SPECIFIC BUSINESS UNIT TANK SIZE REQUIREMENTS ARE RECOMMENDED. TANK SIZING MODELS CAN BE RUN BY CONTACTING FUEL SYSTEM DESIGN DOUBLE WALL FRP ENTRY FITTINGS. TESTING OF PRODUCT LINES SHALL BE PERFORMED PRIOR TO BACK FILL, PRIOR TO PAVING AND BEFORE W !�
<br /> MANAGER — AMERICAS. STATION OPERATION. SEE SITE SPECIFIC DETAIL SHEETS FOR INSTALLATION DETAILS. a a
<br /> LOCATION OF TANKS AND ASSOCIATED EQUIPMENT ON PROPERTY: FINAL FACILITY EQUIPMENT LOCATIONS INCLUDING PLACEMENT AND ***NOTE*** "FIBERCAST SYSTEMS" PIPING TO BE INSTALLED PER MANUFACTURER'S INSTALLATION MANUAL AND SHALL ONLY BE INSTALLED BY D
<br /> ORIENTATION OF TANKS, EMERGENCY SHUTOFF SWITCHES, OVERFILL ALARMS (IF PRESENT) TO BE APPROVED 6Y BP DISTRIBUTION PRIOR QUALIFIED INSTALLERS CERTIFIED BY THE MANUFACTURER. 2
<br /> TO SUBMITTAL FOR PERMITS TO ENSURE CLEAR AND SAFE ACCESS TO THE UNDERGROUND TANKS FOR UNLOADING OPERATIONS. THE FILTER FABRIC: IT IS THE CONTRACTORS RESPONSIBILITY TO PROVIDE FOR THE INSTALLATION OF FILTER FABRIC (DUPONT TYPAR OR MIRAFI c11
<br /> GENERAL CONTRACTOR IS RESPONSIBLE FOR CONFIRMING APPROVED TANK AND EQUIPMENT LOCATIONS HAS BEEN DOCUMENTED W/ BP 500X) WHICH IS REQUIRED FOR WET HOLE INSTALLATIONS ONLY. FABRIC MUST EXTEND 1' ABOVE MAX. HIGH WATER TABLE AND MAY BE CALIFORNIA VARIANT: IN ADDITION TO THE ABOVE, PIPING TO BE INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB-2481 G Qy'
<br /> COMMENCEMENTDISTRIB E SITE ENGINEER AND/OR OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER PRIOR TO THE PINNED TO SIDE OF HOLE WITH WIREK. , ETC. SEAMS MUST BE LAPPED 1' MINIMUM. REQUIREMENTS <T7NG ENG�N��
<br /> TANKS: WET HOLE BALLAST OPTION:
<br /> SHALL BE UNDERWRITERS LABORATORY APPROVED LISTED FOR THE UNDERGROUND STORAGE OF ALL FLAMMABLE AND COMBUSTIBLE MOTOR FUELS WATER IS THE SUITABLE MEDIUM FOR BALLAST DURING WET HOLE TANK INSTALLATIONS. A PROPERLY INSTALLED 12 FOOT HIGH TEMPORARY VENT PIPE (9) VENT PIPING INSTALLATION: 18215 72ND AVENUE SOUTH
<br /> AS CALLED FOR ON THE SITE SPECIFIC DRAWING OR AS DESIGNATED ON THE SUPPLEMENTAL CONDITIONS AND SHALL BE DOUBLE WALL TANKS OF MUST BE INSTALLED BY THE CONTRACTOR, IF WATER IS USED TO BALLAST TANKS, THE WATER IS TO BE COMPLETELY PUMPED OUT & MOPPED DRY IN
<br /> FIBERGLASS REINFORCED PLASTIC (FRP). INSTALLATION OF TANKS AND PIPING SHALL BE IN ACCORDANCE WITH U.L. LISTED MANUFACTURER'S ORDER TO PROTECT FUEL INTEGRITY. CONTRACTOR IS REQUIRED TO COORDINATE BALLASTING OPERATIONS WITH OWNER'S REPRESENTATIVE OR HIS AGENT, STANDARD: CONTRACTOR TO INSTALL 2" INDIVIDUAL SINGLE WALL FIBERGLASS VENT PIPING, CONNECTORS, VALVES AND FITTINGS TO THE FILL SIDE KENT, WA 98032
<br /> INSTRUCTIONS. INSTALLATION SHALL CONFORM TO NFPA-30/30A AND ALL APPLICABLE LOCAL, STATE AND FEDERAL REGULATIONS. TANKS SHALL THE BP PROJECT MANAGER. IT IS THE INSTALLING CONTRACTOR'S RESPONSIBILITY TO DETERMINE THE JURISDICTIONAL REQUIREMENTS AND ACCEPTANCE SUMPS ON TANKS AS INDICATED ON SITE SPECIFIC FUELING PLAN AND ACCOMPANYING DETAILS. CONTRACTOR TO PROVIDE AT LEAST 4 FEET OF (425)251-6222
<br /> ONLY BE INSTALLED BY QUALIFIED INSTALLERS CERTIFIED BY THE STATE IN WHICH THE TANKS ARE TO BE INSTALLED AND BY THE TANK FOR BALLASTING THE TANKS AND TO PROVIDE FOR PROPER DISPOSAL OF THE BALLASTING MEDIUM UNDER THE REGULATIONS OF THE GOVERNING PIPING RUN BEFORE A CHANGE OF DIRECTION OF 30 DEGREES OR MORE IN ORDER TO PROVIDE MECHANICAL FLEXIBILITY PER CODE REQUIREMENTS. (425)251-8782 FAX
<br /> MANUFACTURER. AUTHORITY. CONTRACTOR TO INSTALL TRACER TAPE WITH VENT PIPING PER TRENCHING DETAILS PENETRATIONS INTO ALL SUMPS SHALL BE MADE WITH SINGLE
<br /> THE UNDERGROUND STORAGE TANK SYSTEM SHALL BE COMPATIBLE WITH THE PRODUCT STORED. ALL CONTINUOUS MONITORING WALL ENTRY FITTINGS VENT PIPING SHALL BE DESIGNED AND INSTALLED FOR SLOPE 1/4" PER FOOT MINIMUM BACK TO TANKS. FOR LONG PIPING CIVIL ENGINEERING, LAND PLANNING,
<br /> BACK FILL: RUNS 1/8" PER FOOT IS ACCEPTABLE. SURVEYING, ENVIRONMENTAL SERVICES
<br /> DEVICES SHALL BE INSTALLED PER MANUFACTURER'S SPECIFICATIONS. CONTRACTOR TO PROVIDE ALL BACK FILL REQUIRED FOR THE PROJECT SCOPE. PEA GRAVEL SHALL CONSIST OF NATURALLY ROUNDED AGGREGATE,
<br /> ALL MATERIALS USED IN THE INSTALLATION SHALL BE COMPATIBLE WITH USE FOR THE INTENDED PURPOSE AS PER NATIONALLY MINIMUM 1/8" AND MAXIMUM 3/4" SIZE. FREE OF CLAY, SLAG, CINDERS, OR DEBRIS. ALL SUBSTITUTES MUST BE APPROVED BY MANUFACTURER AND CONTRACTOR TO INSTALL ABOVE GROUND RISERS AND MOUNTING RACK AS DETAILED ON THESE PLANS. TERMINATION POINT OF TANK VENTS TO BE NO. DATE REVISION DESCRIPTION
<br /> RECOGNIZED CODES, LOCAL CODES AND GOVERNING AUTHORITIES. OWNERS FIELD REPRESENTATIVE. A MINIMUM OF 12' ABOVE GRADE AND NOT WITHIN 5' FROM ANY BUILDING OPENING OR PROPERTY LINE THAT CAN BE BUILT UPON. VENT RISERS 1 9-6-16 PERMIT SUBMITTAL
<br /> METHANOL COMPATIBILITY: FOR ALL METHANOL COMPATIBLE STORAGE SYSTEMS, ALL READILY ACCESSIBLE COMPONENTS SHALL BE METHANOL NO MORE THAN 5% (BY WEIGHT) MAY PASS THE #8 SIEVE FOR BACK FILLING NONMETALLIC TANKS WITH A 96% TO 98% FREE FALL COMPACTION. DRY SHALL BE INSTALLED IN ACCORDANCE WITH NFPA-30, INTERNATIONAL AND UNIFORM FIRE CODE REQUIREMENTS AND CARB EVR REQUIREMENTS.
<br /> COMPATIBLE FOR THE IMMEDIATE INTENDED SERVICE. PEA GRAVEL DENSITY MINIMUM OF 95 POUNDS PER CUBIC FOOT IS REQUIRED. SUPPLY QUARRY CERTIFICATION MEETING ASTM C-33, PARAGRAPH 9.112-14-16 PERMIT RESUBMITTAL
<br /> REQUIREMENTS. CONTRACTOR TO INSTALL TWO (2) 1" SPARE CONDUITS FROM VENT STACK TO INTRINSICALLY SAFE WIREWAY IN BUILDING FOR FUTURE TANK SYSTEM 3 1-31-17 PERMIT RESUBMITTAL
<br /> DIAGNOSTICS.
<br /> BACK FILLING OF TANK EXCAVATIONS SHALL BE PROVIDED IN LIFTS AS PER TANK MANUFACTURER'S INSTALLATION INSTRUCTIONS. a 8-16-17 CONSTRUCTION RELEASE
<br /> INITIAL TANK TESTING: PRODUCT, VENT, AND VAPOR PIPING SHALL BE LAID AND CONTINUOUSLY SUPPORTED ON A 6" BED OF COMPACTED PEA GRAVEL. BLOCKS, PLANKS, CONTRACTOR TESTING OF VENT LINES SHALL BE PERFORMED PRIOR TO BACK FILL, PRIOR TO PAVING AND BEFORE STATION OPERATION. SEE SITE
<br /> CONTRACTOR SHALL COMPLETE ALL TESTING ACCORDING TO MANUFACTURER'S INSTRUCTIONS FOR TANKS. CONTRACTOR SHALL COMPLETE ALL OR OTHER DEBRIS SHALL NOT BE USED TO SUPPORT PIPING IN FINAL INSTALLATION. SPECIFIC DETAIL SHEETS FOR INSTALLATION DETAILS. SEE FIBERGLASS PIPING MANUFACTURER SPECIFICATION BELOW. 5Q 11-1a-17 REV. FOR CONSTRUCTION
<br /> WARRANTY VALIDATION TESTING AND PROVIDE DOCUMENTATION TO OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER. NOTE: UNDER NO CIRCUMSTANCES SHALL DIRT, PAVING MATERIALS, WOOD, OR OTHER CONSTRUCTION DEBRIS BE ALLOWED TO REMAIN IN TANK AND VENT PIPING SPECIFICATION:
<br /> IMMEDIATELY BEFORE INSTALLATION, ALL UNDERGROUND STORAGE TANKS SHALL BE TESTED. HYDROSTATICALLY MONITORED DOUBLE WALL TANKS PIPE EXCAVATIONS.
<br /> SHALL BE TESTED ACCORDING TO MANUFACTURER'S INSTRUCTIONS BY: (2) ANNULAR SPACE HYDROSTATIC MONITOR AND RISER INSTALLATION: FIBERCAST SYSTEMS: RED THREAD II PIPE AND FITTINGS (USED FOR SINGLE WALL). WHERE DOUBLE WALL SYSTEMS ARE REQUIRED FOR ALL VENT
<br /> * INSPECT AND ADJUST RESERVOIR LEVELAND VAPOR PIPING, USE SIZE OVER SIZE RED THREAD II PIPING AND FITTINGS. USE ONLY FIBERCAST SYSTEMS ALCOHOL COMPATIBLE ADHESIVES.
<br /> STANDARD: CONTRACTOR TO INSTALL 4" FIBERGLASS RISER AND VEEDER ROOT HYDROSTATIC SENSOR AT TANK ANNULAR SPACE LOCATION NOTED ALL PIPING AND FITTINGS SHALL BE UL-971 LISTED IN COMPLIANCE WITH THE JULY 2005 PERFORMANCE STANDARDS. 0
<br /> * VISUALLY INSPECT THE TANK EXTERIOR FOR COLORED MONITORING FLUID ON THE PLANS PER MANUFACTURERS INSTRUCTIONS.
<br /> * PRESSURIZE THE PRIMARY TANK 5 PSI AND SOAP TEST ALL FITTINGS. DO NOT PRESSURIZE THE ANNULAR SPACE PIPING TO BE INSTALLED PER MANUFACTURER'S LISTED INSTRUCTIONS AND SHALL ONLY BE INSTALLED BY QUALIFIED INSTALLERS CERTIFIED BY THE
<br /> VISUALLY INSPECT THE TANK INTERIOR
<br /> OR FOR ACCUMULATION OF COLORED MONITORING FLUID. (3) TANK SUMP INSTALLATION: MANUFACTURER. PROVIDE AT LEAST 4' OF STRAIGHT PIPING RUN BEFORE A CHANGE OF DIRECTION OF MORE THAN 30 DEGREES AND INSTALL
<br /> ***NOTE*** FLEXIBLE CONNECTORS AT THE VENT AND VAPOR CONNECTION AT THE TANK SUMPS, AND DISPENSER SUMPS.
<br /> NOTE HYDROSTATIC FLUID RESERVOIR LEVEL MUST BE RECHECKED TO VERIFY TANK INTEGRITY PRIOR TO INTRODUCING BALLAST INTO TANKS. STANDARD: CONTRACTOR TO INSTALL 42" OR 48" DIAMETER TURBINE SIDE AND 42" DIAMETER FILL SIDE FIBERGLASS POLYSIDED SUMPS ON TANKS PER
<br /> MANUFACTURER'S INSTRUCTIONS. NOTE THAT THE ORIENTATION OF THE TANK SUMPS MUST BE CORRECT IN ORDER TO FACILITATE CORRECT PIPING
<br /> FIELD REPAIR OF TANKS: IT IS ALLOWABLE TO FIELD REPAIR DAMAGED TANKS AFTER APPROVAL BY BP FILED ENGINEER. ALL TANKS DAMAGED IN
<br /> INSTALLATION INTO THE SUMPS. SEE ACCOMPANYING DETAILS IN PLAN SET AND NOTE SIZES OF SUMPS PER PROJECT DEMOGRAPHICS. SEAL:
<br /> TRANSPORT OR OFF SHALLE—COPE ATIONREPAS SHALL
<br /> TANS ORBE LDUSE.PARED FIELD B TANKEMANUFAWORK ST HALL CDOTIFIED IELDCOP ESICE REPRESENTANDA LIVE. TANK
<br /> K ARCO BRANDED VARIANT: 42" DIAMETER FILL SIDE AND 48" DIAMETER TURBINE SUMPS ARE INSTALLED. QRpFESSIMANUFACTUONgZ
<br /> SERVICE DOCUMENTATION SHALL BE PLACED IN THE PROJECT FILE AND INTO OWNERS OPERATING FILE. CALIFORNIA VARIANT: SUMPS TO BE DOUBLE WALLED AND INSTALLED WITH CONTINUOUS HYDROSTATIC MONITORING DEVICE PER AB-2481 REQUIREMENTS. JURISDICTIONAL VARIANT: INSTALL DOUBLE WALL SIZE OVER SIZE FIBERGLASS PIPING WHEN REQUIRED BY AUTHORITY HAVING JURISDICTION.
<br /> CALIFORNIA VARIANT: VENT PIPING TO BE DOUBLE WALLED AND INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB-2481 HAL P. GRUBB
<br /> TANK MEASUREMENTS: REQUIREMENTS
<br /> THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE COMPLETION OF THE FOLLOWING TANK MEASUREMENT ACTIVITIES: / =, 87
<br /> ^
<br /> 1. VERIFY THE EXTERNAL SIZE OF THE TANK TO MATCH WITH MANUFACTURER SUPPLIED SHOP MEASUREMENTS. (4) TANK LEVEL GAUGE INSTALLATION: //� O11 STAGE it VAPOR RECOVERY PIPING INSTALLATION:
<br /> TRANSFER THE SIZE, SERIAL NUMBER, AND PRODUCT INSTALLED, AND POSITION OF TANK TO THE AS-BUILT PLAN. l 1
<br /> 2. TRANSFER TANK DIMENSIONAL AND PRODUCT INFORMATION TO THE DATA SHEET IN THE TANK GAUGE CONSOLE. STANDARD: CONTRACTOR TO INSTALL VEEDER ROOT MAGNOSTRICTIVE PROBE LEVEL GAUGE AT OPENING IN FILL SUMP AT LOCATION NOTED ON PLANS
<br /> 3. PROVIDE THE TOP OF TANK ELEVATION READING AT BOTH ENDS OF EACH TANK. PER MANUFACTURER'S INSTALLATION INSTRUCTIONS. STANDARD: CONTRACTOR TO INSTALL 3" SINGLE WALL FIBERGLASS STAGE II VAPOR RECOVERY HEADER, CONNECTORS, VALVES AND FITTINGS TO THE met
<br /> LOWEST OCTANE GRADE FILL SIDE SUMP AS INDICATED ON SITE SPECIFIC FUELING PLAN AND ACCOMPANYING DETAILS. NOTE THAT THE 1ST I V o-
<br /> L TANKS
<br /> DEFLECTION DEFLECTION
<br /> MEASUREMENT
<br /> PROCEDURE:
<br /> AFTER TANK INSTALLATION SHALL BE ACCORDING TO MANUFACTURER'S REQUIREMENTS AND SHALL BE (5) FILL AND STAGE I VAPOR RECOVERY INSTALLATION: SHALL BTE MADEION OWITHA2". CONTRACTORGE 11 VAPOR TO INSTALL OVERY TO 2 R DUCTING TEES WHEREER TO LOWEST OCTANE TANK HLL EADERS S BRANCHHTO DISPENSERS.ER MAXIMTO UM
<br /> CONNECTIONS2)A
<br /> MEASUREMENT BEFOREAND DISPENSERS TF OF C40F���pn
<br /> WITHIN MANUFACTURER'S TOLERANCES. ALL INFORMATION SHALL BE COMPLETED AS PER THE MANUFACTURER'S WARRANTY DOCUMENTATION. STANDARD: CONTRACTOR TO INSTALL 4" GALVANIZED FILL AND STAGE I VAPOR RECOVERY RISERS AT FILL SIDE SUMPS. CONTRACTOR TO INSTALL DROP PER 2" BRANCH. CONTRACTOR TO PROVIDE AT LEAST 4 FEET OF PIPING RUN BEFORE A CHANGE OF DIRECTION OF 30 DEGREES OR MORE IN
<br /> TUBE ASSEMBLY. CONTRACTOR TO INSTALL EXTRACTOR FITTING AND BALL FLOAT VALVE AT STAGE I VAPOR RETURN RISER. CONTRACTOR TO INSTALL ORDER TO PROVIDE MECHANICAL FLEXIBILITY PER CODE REQUIREMENTS. CONTRACTOR TO INSTALL TRACER TAPE WITH VAPOR PIPING PER TRENCHING
<br /> VENT AND STAGE II FLEX CONNECTORS AND FRP ADAPTERS. LOCATE AND CUT PENETRATIONS INTO SUMPS FOR THE ROUTING OF VENT AND STAGE II DETAILS PENETRATIONS INTO ALL SUMPS SHALL BE MADE WITH DOUBLE WALL ENTRY FITTINGS. STAGE II VAPOR RECOVERY PIPING SHALL BE z
<br /> VAPOR PIPING INTO SUMPS AND MAKE CONNECTIONS TO VENT AND VAPOR PIPING FIBERGLASS PIPING. CONTRACTOR TO INSTALL DOUBLE SIDED DESIGNED AND INSTALLED FOR 1/4" PER FOOT MINIMUM SLOPE BACK TO TANKS. AT LARGE SITE LAYOUTS, 1/8" PER FOOT MINIMUM IS =
<br /> PENETRATION ENTRY BOOTS FOR ALL ENTRIES INTO SUMPS. CONTRACTOR TO INSTALL STATIC GROUNDING SYSTEM AT ALL FILL AND VAPOR RISERS PER ACCEPTABLE IF IT AVOIDS USING A KNOCK OUT SUMP (VAPOR POT) OR HAVING EXCESSIVE TANK DEPTH. CONSULT OWNER'S REPRESENTATIVE OR z
<br /> INSTALLATION DETAILS SHOWN ON SHEET G.0.7. HIS AGENT, THE BP PROJECT MANAGER, WHERE DISCREPANCIES OCCUR.
<br /> CONTRACTOR TO INSTALL CARB APPROVED STAGE I MULTIPORT MANHOLES WITH 5 GALLON SPILL COLLECTION BUCKETS. INSTALL PRODUCT AND FILL CONTRACTOR TESTING OF STAGE II VAPOR LINES SHALL BE PERFORMED PRIOR TO BACK FILL, PRIOR TO PAVING AND BEFORE STATION OPERATION. o
<br /> ADAPTERS AND CAPS. SEE ACCOMPANYING DETAILS IN SITE SPECIFIC PLAN SET FOR MANUFACTURER AND INSTALLATION REQUIREMENTS. 0
<br /> DOUBLE WALL SEE SITE SPECIFIC DETAIL SHEETS FOR INSTALLATION DETAILS. SEE FIBERGLASS PIPING MANUFACTURER SPECIFICATION BELOW.
<br /> FRP TANKDOUBLE WALL ACD BRAD v RIA : DUA FLLS AN DUAL STA E VA OR R URNS RE 0 E NS ALL D I C ST M UL IPO T QU D" AN
<br /> I.D.='A' OL 0THE STAGE II PIPING SPECIFICATION: o
<br /> FRP TANK I.D.="B" 25,000 GALLON TANK ONLY. VENT AND STAGE II TANK CONNECTION AND VENT AND VAPOR PIPING IS INSTALLED IN THE FILL SIDE SUMP PER DETAILS. DEVELOPMENT INFORMATION:
<br /> 05 FIBERCAST SYSTEMS: RED THREAD II PIPE AND FITTINGS (USED FOR SINGLE WALL). WHERE DOUBLE WALL SYSTEMS ARE REQUIRED FOR ALL VENT ARCO NTI
<br /> AND VAPOR PIPING, USE SIZE OVER SIZE RED THREAD II PIPING AND FITTINGS. USE ONLY FIBERCAST SYSTEMS ALCOHOL COMPATIBLE ADHESIVES.
<br /> ALL PIPING AND FITTINGS SHALL BE UL-971 LISTED IN COMPLIANCE WITH THE JULY 2005 PERFORMANCE STANDARDS. MODIFIED a
<br /> M
<br /> PIPING TO BE INSTALLED PER MANUFACTURER'S LISTED INSTRUCTIONS AND SHALL ONLY BE INSTALLED BY QUALIFIED INSTALLERS CERTIFIED BY THE 3000 am/pm o
<br /> (6) TURBINE INSTALLATION: MANUFACTURER. PROVIDE AT LEAST 4' OF STRAIGHT PIPING RUN BEFORE A CHANGE OF DIRECTION OF MORE THAN 30 DEGREES AND INSTALL W/ 26'x65' CAR WASH
<br /> FLEXIBLE CONNECTORS AT THE VENT AND VAPOR CONNECTION AT THE TANK SUMPS, AND DISPENSER SUMPS.
<br /> BEFORE BACK FILL AFTER BACK FILL STANDARD: CONTRACTOR TO INSTALL FE PETRO IST 2 HP VARIABLE SPEED TURBINES AND PIPING CONNECTION VALVES AND FITTINGS IN TANK FUEL CANOPY W/ 8 MPD'S
<br /> SUMPS AS SHOWN ON SITE SPECIFIC DETAIL DRAWINGS. ALL PRODUCT LINES TO TURBINES TO BE EQUIPPED WITH 3 GPH ELECTRONIC LINE LEAK JURISDICTIONAL VARIANT: INSTALL DOUBLE WALL SIZE OVER SIZE FIBERGLASS PIPING WHEN REQUIRED BY AUTHORITY HAVING JURISDICTION.
<br /> TANK INSPECTION AND INSTALLATION — DEFLECTION MEASUREMENT DETECTION. LEAK DETECTORS ARE TO BE TESTED FOR THE 3 GPH LEAK DETECTION PRIOR TO START UP. CONTRACTOR TO PROVIDE TEST DATA AT slrE ADDRESS:
<br /> THE TIME OF PUNCH LIST AS WELL AS INCLUDE IN CLOSE OUT BINDER. ALL TURBINES ARE EQUIPPED WITH STANDARD "R" CHECK VALVE AS A
<br /> DIPSTICK PREPARATION STANDARD FROM FACTORY. SET TURBINE INTAKES AT 5" FROM BOTTOM OF TANKS. TURBINES TO BE EQUIPPED WITH INTAKE FILTER SCREENS. CALIFORNIA VARIANT: STAGE II VAPOR PIPING TO BE DOUBLE WALLED AND INSTALLED WITH CONTINUOUS VACUUM MONITORING DEVICE PER AB-2481
<br /> DRIVE A SMALL HEADED, NON—SPARKING (E.G. BRASS) NAIL HALFWAY INTO A WOODEN DIPSTICK, 1 INCHCONTRACTOR TO INSTALL 1" RIGID STEEL CONDUITS FOR SUBMERSIBLE PUMP POWER. (ONE FOR EACH TURBINE). CONTRACTOR IS TO LABEL REQUIREMENTS. ALL CONNECTIONS TO THE TANKS SHALL BE MADE WITH 3 TRINITY PARKWAY E
<br /> ABOVE ITS BASE. TURBINES AND CONTROLLERS AS TO WHICH PRODUCT THEY SERVE. GREEN CONTROLLER LIGHTS ARE TO GO OUT WHEN TURBINES ARE OFF OR @ SCOTT CREEK DRIVE
<br /> FIRST DIAMETER READING (PRIOR TO BACK FILL) LOSE POWER. IST PUMP CONTROLS ARE TIED TO VEEDER ROOT TLS-350. SEE APPROPRIATE TURBINE CONFIGURATION AND PROGRAMMING SHEETS. THERE ARE (4) FOUR STAGE II EVR WITH ISD DESIGN CHOICES THAT MAY BE INCORPORATED INTO THE UST SYSTEMS IN CALIFORNIA. STOCKTON,CA o
<br /> 1. PLACE THE DIPSTICK INTO A SERVICE FITTING. 1. VEEDER ROOT CARBON CANISTER VAPOR POLISHER WITH VST BALANCE HANGING HARDWARE AND VEEDER ROOT ISD COMPONENTS.
<br /> 2. MEASURE AND RECORD THE DISTANCE FROM THE TANK BOTTOM TO THE TOP OF THE FITTING. SINGLE MASTER TURBINE CONFIGURATIONS — EQUIPPED AS NOTED ABOVE. SEE APPROPRIATE SITE SPECIFIC DRAWINGS FOR INSTALLATION DETAILS. 2. HEALY CLEAN AIR SEPARATOR WITH HEALY VACUUM ASSIST HANGING HARDWARE AND VEEDER ROOT ISD COMPONENTS. 3
<br /> 3. PULL THE DIPSTICK UP UNTIL THE EXPOSED NAIL CATCHES ON THE INSIDE TOP OF TANK. 3. VST ECS VAPOR PROCESSOR WITH VST BALANCE HANGING HARDWARE AND VEEDER ROOT ISD COMPONENTS. FACILITY # TBD
<br /> 4. MEASURE THE DISTANCE FROM THE TANK TOP (INSIDE) TO THE TOP OF THE FITTING. SUBTRACT 1 4. VST BALANCE HANGING HARDWARE WITH FRANKLIN FUELING/HEALY CLEAN AIR SEAPARATOR AND VEEDER ROOT ISD COMPONENTS.
<br /> DESIGNED BY: ALLIANCE ZBrDM: N
<br /> INCH FROM THIS MEASUREMENT AND RECORD THE DISTANCE. _ __
<br /> 5. SUBTRACT THE SECOND DISTANCE FROM THE FIRST AND RECORD THIS VALUE AS READING "A" ON THE SEE GENERAL SHEETS G.0.6 SERIES DRAWINGS FOR DESIGN INTENT DETAILS ON THE ABOVE SYSTEMS. GrTcum er eP REPM: cJ
<br /> INSTALLATION CHECKLIST.
<br /> SECOND DIAMETER READING (AFTER BACKFILL) DRAWN BY., ALLIANCE PM:
<br /> 1. PLACE THE DIPSTICK INTO A SERVICE FITTING WITH A STANDPIPE INSTALLED TO SUBGRADE. 1OA� DECOMMISIONING STAGE II VAPOR RECOVERY: VERSION: PROJECT NO: CD0
<br /> 2. MEASURE AND RECORD THE DISTANCE FROM THE TANK BOTTOM TO THE TOP OF THE STANDPIPE. STANDARD: FOR PROJECTS INVOLVING THE DECOMMISSIONING OF STAGE II VAPOR RECOVERY SYSTEMS, G.C. IS TO VERIFY WITH THE AUTHORITY _ 16700 00
<br /> 3. PULL THE DIPSTICK UP UNTIL THE EXPOSED NAIL CATCHES ON THE INSIDE TOP TANK. HAVING JURISDICTION THAT STAGE II IS NO LONGER REQUIRED AT A SPECIFIC FACILITY BEFORE INITIATING THE DECOMMISSIONING WORK AND WHICH
<br /> 4. MEASURE THE DISTANCE FROM THE TANK TOP (INSIDE) TO THE TOP OF THE STANDPIPE.
<br /> PIPE. SUBTRACT 1 DRAWING TITLE:
<br /> DECOMMISSIONING PROCEDURES ARE REQUIRED TO BE IMPLEMENTED. SEE SHEET G.0.6.15. FOR GENERAL REQUIREMENTS AND PROCEDURES. i
<br /> INCH FROM THIS MEASUREMENT AND RECORD THE DISTANCE.
<br /> 5. SUBTRACT THE SECOND DISTANCE FROM THE FIRST AND RECORD THIS VALUE AS READING "B" ON THE CONSULT OWNER'S REPRESENTATIVE OR HIS AGENT, THE BP PROJECT MANAGER, WHERE DISCREPANCIES OCCUR BETWEEN THE CONTRACT TANK AND PIPING o
<br /> DOCUMENTS AND THE REQUIREMENTS OF THE AUTHORITY HAVING JURISDICTION. SCOPE OF WORK
<br /> INSTALLATION CHECKLIST. AND GENERAL NOTES o
<br /> CALCULATION AND COMPARISON
<br /> 1. SUBTRACT READING "B" FROM READING "A". (FRP 1 OF 2) q
<br /> 2. COMPARE THIS VALVE TO THE TABLE OF "MAXIMUM ALLOWABLE DEFLECTIONS" SHOWN ON THE
<br /> "INSTALLATION CHECKLIST sNEer No: E
<br /> 3. VERTICAL DEFLECTION IN EXCESS OF THESE VALUES INDICATES IMPROPER INSTALLATION AND VOIDS THE o
<br /> TANK WARRANTY. OCD
<br /> MAXIMUM DEFLECTION FOR 8'-0" TANKS = 1-1/4"
<br /> MAXIMUM DEFLECTION FOR 10'-0" TANKS = 1-1/2" G .O,�. /