0 • <br /> A5.0 ESTIMATED SCHEDULE <br /> It is estimated that it would take about six weeks to complete the work in this <br /> delivery order (see Figure A-4). Site reconnaissance and mobilization (Task 1) <br /> and exposure of tank and piping (Task 2) would require about one week together. <br /> The removal of piping (Task 3) and tank (Task 4) will start simultaneously; it would <br /> take the next two weeks. The disposal of piping, tanks, and tank contents (Tasks 3 <br /> and 4) will start during the third week complete during the fourth week. Following <br /> this, sampling and analysis of soil (Task 5) will be performed. This task will take <br /> about two weeks to complete. Analytical turnaround time is 10 working days, <br /> unless rush analysis is ordered. Tank closure report preparation (Task 9) will start <br /> on the 5th week and is expected to be completed in 2 weeks. <br /> A-6 <br />