Laserfiche WebLink
2905 Benjamin Holt Compliance Summary <br /> 1989 Chevron promises to investigate and remediate the site. In early February, Chevron <br /> agreed to submit a work plan in March and a problem assessment report by late April. <br /> Five monitoring wells were installed in late February. In September, the CVRWQCB <br /> required additional investigation to determine the full extent of the contamination. <br /> Quarterly groundwater monitoring was initiated in March. <br /> 1990 In early April, Chevron notifies the CVRWQCB that a work plan to continue the <br /> investigation would be submitted by the end of the month. In early May, Chevron <br /> requests an extension until mid June. In early May the CVRWQCB approves the <br /> extension and directs Chevron to submit a PAR by late August. In late July, the <br /> CVRWQCB informs Chevron that the work plan submitted will not adequately <br /> investigate the contamination. In September, PHS/EHD notifies Chevron to submit <br /> permit applications and encroachment agreements. <br /> 1991 In February, PHS/EHD approves the installation of BAT probes, but not in lieu of <br /> monitoring wells. In March five bat probes are installed. In December, PHS/EHD <br /> notifies Chevron that the groundwater plume has not been defined nor a remedial <br /> action plan submitted. PHS/EHD directs Chevron to submit a new work plan or <br /> implement the June 1990 work plan by mid February. <br /> 1992 In January, a meeting is held at the CVRWQCB and Chevron agreed to install the <br /> additional wells by March 1 and submit a PAR by June. In February, a second <br /> addendum to the June 1990 work plan was submitted for the installation of two MWs <br /> and one vadose well. In March, monitoring wells, MW6 and MW7 and vapor zone well, <br /> VW1, were installed. In December, PHS/EHD notified Chevron that either a problem <br /> assessment report or a work plan to complete the investigation should be submitted by <br /> February 1, 1993. PHS/EHD also indicated that a municipal well sampling plan has <br /> not been submitted as directed, that there had been no discussion about the <br /> disposition of contaminated soil from the tank removal and site investigation nor about <br /> the BAT system probes. <br /> 1993 In January, Chevron agreed to the following schedule: <br /> 1/29/93 Submit fourth quarterly report <br /> 2/7/93 First quarter sampling at site and Muni Well#10 <br /> 3/15/93 Work Plan to install well downgradient of MW6 <br /> 4/7/93 Submit first quarterly report <br /> 4/15/93 Drill well downgradient of MW6 <br /> 6/30/93 Submit PAR and proposal to destroy BAT probes <br /> In March, the work plan to install MW8 was approved. Negotiations between Chevron <br /> and the City of Stockton continued and the well installed in December. PHS/EHD <br /> directed Chevron to initiate work on the PAR for submittal in late October. In late <br /> September, Chevron requests an extension for the PAR submittal until early <br /> December. In late November, Chevron's consultant informs PHS/EHD that a PAR <br /> would be submitted by late February 1994. <br /> 1994 In March, Chevron submits the second and third quarter 1993 monitoring reports. In <br /> March, Chevron's consultant stated that a PAR/RAP would be submitted later that <br /> month. Chevron submits a PAR/Feasibility Study that proposed additional <br /> investigation. In April, PHS/EHD informed Chevron that extensions were granted so <br /> that all the necessary investigation and feasibility studies could be conducted. <br /> PHS/EHD directed Chevron to submit by 5/2/94 a work plan, to complete within 45 <br /> days the field work and feasibility studies and to submit a PAR addendum by 7/15/94. <br />