WORK PLAN- MW-10 AND -11 <br /> PURPOSE <br /> The purpose of this work plan is to provide further Easterly and Northeasterly horizontal <br />{ delineation of the plume in the 45-80' sand layer. <br /> SELECTION OF LOCATION AND DEPTH OF -10 AND -11 <br /> There are three layers of concern. One sand layer at 20-40', another sand layer at 45-80' and the <br /> clays and silts at 90-100' which may receive leachate from the second sand layer above. The <br /> prominent direction of ground water flow is N 60° E with a gradient s=0.004. <br /> The 20-40' sand layer is bounded on the West and the South by the bearing of the gradient. The <br /> 20-40' sand layer is bounded on the North by CPT#3. The 20-40' sand layer is unbounded on <br /> the East. The narrowing of the 20-40' sand layer indicates that the horizontal limits will <br /> terminate before reaching new well MW-10. The bore logs for MW-10 will be consulted to see <br /> if a shallow well is needed. <br /> The 45-80' sand layer is bounded on the West and the South by the bearing of the gradient. The <br /> 45-80' sand layer is bounded to the North by CPT#5. The 45-80' sand layer is unbounded to the <br /> North/East (bearing of gradient) and on the East. MW-10 and MW-11 will be installed to <br /> provide data for the Northern and Easterly quadrant. The bore logs will be consulted when <br /> drilling, in order to set the tip at the bottom of the sand layer. A 10' screen length will be used to <br /> avoid cross contamination of adjacent sand layers. <br /> The clays and silts below the 45-80' sand layer are bounded on the West and on the South by the <br /> bearing of the gradient and on the North by CPT-3 and on the East by MW-81). <br /> EXECUTION OF -10 AND -11 <br /> The proposed well section is located in Exhibit A. The proposed well layout is in Exhibit B and <br /> an isometric layout of the lithology is in Exhibit C. The layout includes the location of all wells <br /> and ept's, and the highest values for TPI-1g, MTBE and 1,2-DCA at depth. The layout also <br /> includes an estimated boundary for TPHg and 1,2-DCA. <br /> Soil samples will be taken on five foot intervals starting at 20' below ground surface to final tip <br /> of well. Soil samples will be tested for BTEX, TPI-1g, Fuel Oxygenates and Fuel Additives. <br /> Well Development will be performed after well installation. Water samples will be taken with <br /> the proceeding quarterly monitoring and tested for BTEX, TPHg, fuel additives, and oxygenates. <br /> Foothill Engineering will obtain permission from the City of Stockton to place MW-10 within <br /> APN#149-095-03 held by the Redevelopment Agency, Foothill Engineering will obtain <br /> permission from Caltrans to install MW-I I between E/B S/R 4 Cross Town Freeway and the off <br />