Laserfiche WebLink
0 <br /> L5.0 SCHEDULE <br /> Upon receiving approval of this work plan, ETIC will initiate field activities. Direct-push <br /> drilling can be performed within-three weeks of obtaining the drilling permit from SJ,CEHD <br /> and encroachment permit from the City of Stockton. Analytical data from the direct-push <br /> borings will be available two weeks following the.field activities. ETIC will submit a <br /> recommendation to SJCEHD for the location of monitoring well MW-5 one week following <br /> receipt of the direct-push analytical data Well.installation will be performed within four <br /> weeks of receiving approval from SJCEHD. Analytical data for soil will be available two . <br /> weeks following the well installations. A written report will-be prepared within 12 weeks <br /> following receipt of the soil data from the well installations. <br /> i <br /> i <br /> { <br /> f <br /> f <br /> 19 <br /> SL-Ce ftr-SCM and Rev.RI WP_2007.09 <br />