Laserfiche WebLink
i <br /> III . Project completion Estimates <br /> The schedule shown below reflects completion of major site cleanup <br /> phases based on current information regarding this site and <br /> responsible party cleanup plans and completed actions . <br /> Task Estimated <br /> Completion Date <br /> 1 . Site Characterization <br /> a ) Preliminary Assessment a ) February 9 , 1990 <br /> b ) Remedial Investigation b ) September 1 , 1990 <br /> C ) Feasibility Study c ) January 1 , 1991 <br /> 2 . Remedial Action Plan January 1 , 1991 <br /> 3 . Remedial Action <br /> a ) Design a ) September 1 , 1990 <br /> b ) Implementation b ) January 1 , 1991 <br /> C ) Certification c ) January 1 , 1993 <br /> ( attach cert . doc . if completed ) <br />