Laserfiche WebLink
immediately (upon approval of the regulatory agencies) , will <br /> concentrate on removing contamination in the soil . The second <br /> phase, to begin after all permits (or negative declaration) are <br />' approved, will concentrate on the groundwater. <br /> 7.1 Soil Remediation <br /> Because the soil contamination continues to - be a source of <br /> contamination for the fluctuating groundwater, GeoAudit believes it <br /> will facilitate groundwater clean-up if the soil is addressed <br /> first. GeoAudit plans to begin work on the contaminated soil as <br /> soon as authorization is received by the client and the FRP has <br /> been reviewed by the CVRWQCB and the PHS/EHD. <br /> 7.2 Groundwater Remediation <br /> The start; of the groundwater remediation will begin upon approval <br /> of the application for a negative declaration. <br /> 8. 0 SITE HEALTH. & SAFETY <br /> A site health and safety plan (SHSP) is included in Appendix F. The <br /> SHSP plan will be posted on-site at all times. <br /> I <br /> I <br /> I <br /> 13 <br />