Laserfiche WebLink
December 30, 1994 • • <br /> Page 7 <br /> Task Completion Date <br /> Remedial strategy approval 02/01/95 <br /> Submit air permit modifications 03/01/95 <br /> Complete design of remedial system 04/01/95 <br /> Obtain building permits 05/15/95 <br /> Prepare bid package -06/01/95 <br /> Purchase capital equipment 07/01/95 <br /> Construction of remedial system 08/31/95 <br /> System start-up 10/01/95 <br /> Implementation of Alternative 1 will follow this schedule, given unforeseen circumstances do <br /> not hinder the pace of implementation. If problems occur that may prohibit the <br /> implementation of the proposed schedule, the schedule will be revised, and the appropriate <br /> parties will be contacted. <br /> If you have any questions, do not hesitate to call our office. <br /> Sincerely, <br /> Pacific Environmental Group, Inc. <br /> Robert L. Giattino <br /> Project Engineer <br /> JOSEPH J. IMNIO <br /> Joseph Muzzio UN 1 <br /> Project Geologist <br /> CEG 1672 qrF of ca��� <br /> Attachments: Figure 1 - Site Location Map <br /> Figure 2 - Extended Site Map <br /> Figure 3 - TPH-g/TPH-d/Oil and grease concentration in soil <br /> cc: Ms. Mary Meays, San Joaquin County Public Health Services - <br /> Environmental Health Division <br /> 3100011 b/wkpin <br />