Draft Supplemental Environmental Impact Report Page 1I-40 <br /> Forward Inc. Landfill 2018 Expansion Project <br /> a. Install temporary fencing at the edge oft e construction area and the <br /> adjacent wetland,marsh,or ditch; <br /> b. Restrict working areas, spoils and equipment storage and other project <br /> activities to areas outside of marshes,wetlands and ditches;and <br /> c. Maintain water quality and limit construction runoff into wetland areas <br /> through the use of hay bales,filter fences,vegetative buffer strips, or <br /> other accepted equivalents. <br /> 6. If on-site wetlands,irrigation ditches,marshes,etc. are being relocated in <br /> the vicinity:the newly created aquatic habitat shall be created and filled <br /> with water prior to dewatering and destroying the pre-existing aquatic <br /> habitat. In addition,non-predatory fish species that exist in the aquatic <br /> habitat and which are to be relocated shall be seined and transported to the <br /> new aquatic habitat as the old site is dewatered. <br /> 7. If wetlands, irrigation ditches, marshes,etc.will not be relocated in the <br /> vicinity,then the aquatic habitat shall be dewatered at least two weeks prior <br /> to commencing construction. <br /> 8. Pre-construction surveys for the giant garter snake (conducted after <br /> completion of environmental reviews and prior to ground disturbance) <br /> shall occur within 24 hours of ground disturbance. <br /> 9. Other provisions of the USFWS Standard Avoidance and Minimization <br /> Measures during Construction Activities in Giant Garter Snake Habitat shall be <br /> implemented (excluding programmatic mitigation ratios which are <br /> superseded by the SJMSCP's mitigation ratios). <br /> H-4. Potential "Take" of Mitigation Measure HA. Participation int e SJMSCP affords the project Less t an <br /> Western Pond Turtle. proponent Incidental Take authorization for western pond turtle pursuant to ESA, Significant <br /> CESA and CEQA. Nonetheless,to minimize the potential for incidental take of the <br /> species,preconstruction surveys for western pond turtles shall be conducted within <br /> rr r■ rr rr s rr �r rr r ar �■ri r rr r� �r r rr rr irr <br />