Laserfiche WebLink
KLEINFELDER <br /> EY.FECT MORE - <br /> 4 SCHEDULE FOR COMPLETION OF WORK <br /> 4.1 APPROXIMATE PROJECT SCHEDULE <br /> Based on the proposed scope of work contained in this workplan the following <br /> approximate project schedule has been formulated: <br /> Anticipated Schedule Task <br /> Business Da s <br /> 2 days Submittal of workplan to RWQCB <br /> 7 — 28 days RWQCB review and comment <br /> 5 — 10 days Conditional Revisions and RWQCB approval of final <br /> workplan <br /> 5 — 10 days Permitting and subcontractor scheduling <br /> 5 — 7 days Monitoring well installation, development and sampling <br /> 5 — 14 days Laboratory analysis <br /> 10 — 15 days Report preparation <br /> 3 days Submittal of Monitoring Well Installation Report to RWQCB <br /> by OLWD/Beck Development <br /> Kleinfelder has no control over the time required by a regulatory agency to review and approve a <br /> workplan and permit applications. <br /> 48093.E01/ST07R052/CJC/Iv Page 8 of 15 <br /> ©2007 Kleinfelder, Inc January 26, 2007 <br />