Table 10. Post Closure Cost Estimate
<br /> Fiscal Year 2019-2048 2019 2020
<br /> Category Assumptions/Notes
<br /> Groundwater monitoring and reporting is based on the schedule as outlined
<br /> in Post Closure Permit. Increased costs in 2028 following cessation of
<br /> 1. GROUNDWATER MONITORING corrective action measures and increased groundwater monitoring effort as $2,022,996 $94,659 $94,659
<br /> outlined in the PC Permit. Reduced costs in 2034 assumes monitoring and
<br /> reporting of POC wells annually under Detection Monitoring.
<br /> Treatment system will operate for the duration of the post closure permit
<br /> 3. TREATMENT SYSTEM O&M (10 years), through 2027. Assumes pulsing of treatment system every $1,421,020 $142,102 $142,102
<br /> quarter; thus, treatment system operates 6 months of the year.
<br /> 4. GENERAL INSPECTION $43,200 $1,440 $1,440
<br /> Inspections of the pond covers are conducted on an annual basis and
<br /> reported in the Annual Groundwater Monitoring Report. Inspections
<br /> 5. COVER AND DRAINAGE SYSTEM MAINTENANCE $24,000 $800 $800
<br /> include observations regarding subsidence, and any changes to topography
<br /> and/or surface water drainage.
<br /> Cost related to O&M of treatment system are captured in Task 3. Well
<br /> redevelopment and repair costs are calculated based on GWM during post
<br /> 6. MONITORING, COLLECTION AND DISPOSAL SYSTEM MAINTENANCE corrective action measures period as that is when the most number of wells $271,076 $11,999 $11,999
<br /> will be sampled. Costs during corrective action measures period and
<br /> detection monitoring period are reduced based on reduced GWM schedule.
<br /> 7. POST CLOSURE PERMIT RENEWALS AND ANNUAL PERMIT FEES $450,000 $5,000 $5,000
<br /> 8. SECURITY (Treatment System) Monthly inspections, repairs (yearly average) $16,021 $1,001 $1,001
<br /> 9. OVERHEAD AND MANAGEMENT COSTS Overhead and management costs reduced in accordance with elimination $265,000 $10,000 $10,000
<br /> of corrective action measures.
<br /> 11. ONE TIME CAPITAL EXPENSES
<br /> Investigation of Shallow Well B-1 $30,000 $30,000
<br /> New Shallow& Intermediate Monitoring Wells Special Conditions included in Post Closure Permit $88,000 $88,000
<br /> Soil Gas and Indoor Air Human Health Risk Assessment $225,000 $100,000 $125,000
<br /> Post Corrective Action Site Wide Groundwater Monitoring and Reporting Site-wide sampling and reporting between Phase I and Phase II GWM. $30,000
<br /> End of Project Removal/Disposal of Carbon Adsorbers and Air Stripper $42,000
<br /> End of Project Removal of Treatment System Equipment, Building, and
<br /> Dismantling, removal and disposal costs at end of project $67,000
<br /> Piping
<br /> End of Project Destruction of Wells $82,000
<br /> 12. LAND USE COVENANT MONITORING Required by Post Closure Permit $40,100 $1,820 $1,320
<br /> ANNUAL TOTALS 1 $5,117,413 1 $486,821 1 $393,321
<br /> Former Kearney-KPF Facility DUDEK
<br /> Stockton, California Page 1 of 4 2/22/2019