COMPLETION AND TESTING OF <br /> NCPA Lodi STIG #1 Injection Well <br /> May 12 - June 9, 1993 <br /> 1.0 SUMMARY <br /> Drilling operations on NCPA Lodi STIG #1 injection well were completed on <br /> May 9, 1993. The well was drilled to a total depth of 4,650 ft, with 7-in. casing cemented at <br /> 3,660 ft in the Nortonville Shale (the confining layer) and a 5-in. liner cemented through the <br /> Domengine formation to a depth of 4,645 ft in the Capay Shale. During the period May 12 - <br /> June 9, 1993, the following operations were carried out to complete and test the well. <br /> • The 5-in. liner was perforated selectively in sands in the lower portion of the <br /> Domengine formation. A net 222 ft of perforations were shot within the interval <br /> 4,234 - 49573 ft. <br /> • The well was produced by nitrogen lift through coil tubing to clean out sand fill, <br /> collect representative water samples from the Domengine formation and to <br /> provide formation water for an injection test. <br /> • A wire-wrapped screen liner was installed and gravel-packed inside the 5-in. liner <br /> for sand control. <br /> • An injection test was performed in conjunction with cased-hole logging to <br /> quantify injectivity, determine the formation transmissivity, define the injection <br /> profile and verify that there is no interzonal flow behind casing. <br /> • A packer and 41/2-in. tubing were installed in the well and pressure tested. <br /> Mesquite Group, Inc. '1 <br />