Table 3
<br /> l
<br /> Monitoring and Remediation Schedule
<br /> Del Monte Plant 33, 110 North Filbert Street
<br /> Stockton, California
<br /> Activity/Document Date Scheduled/Completed
<br /> Remedial Investigation/Feasibility Study February, 1992
<br /> Underground Pipe Removal and Soil Investigation April 23, 1992
<br /> Groundwater Monitoring (MW-1 through 7D) June 30, 1992
<br /> Groundwater Monitoring Report August 6, 1992
<br /> Groundwater Monitoring MW-3, -4,,-6, -7S, 7D) October 1, 1992
<br /> Groundwater Monitoring Report October 19, 1992
<br /> Groundwater Monitoring MW-3, -4, -6, -7S; 7D) January 21, 1993
<br /> Groundwater Monitoring Report February 10, 1993
<br /> Groundwater Monitoring (MW-3, -4, -6, -7S, 7D) March 29, 1993
<br /> Groundwater Monitoring Report May 3, 1993
<br /> Soil and Groundwater Remediation (Phase I) Design June 30, 1993
<br /> Specification Submittal (to Del Monte)
<br /> Groundwater Monitoring (MW-1, -2, -3, -4, -6, -7S, -7D) June 30, 1993
<br /> Groundwater Monitoring Report July 30, 1993
<br /> Contractor Bid Submittal (to Del Monte) August 15, 1993
<br /> Contractor Award September 15, 1993
<br /> Groundwater Monitoring (MW-3, -4, -6, -7S, 7D) September 30, 1993
<br /> Groundwater Monitoring Report October 30, 1993
<br /> Commence Equipment Procurement and Remediation November 1, 1993
<br /> System Construction
<br /> Groundwater Monitoring (MW-3, -4, -6, -7S, 7D) December 30, 1993
<br /> Groundwater Monitoring Report January 30, 1994
<br /> Remediation System Startup January, 1994
<br /> Remediation System O&M Ongoing