Dei Monte AS/cat Cast.Est <br /> 1+ Del Monte Plant 33 <br /> Air Stripper and Offgas Control (catalytic oxidation) <br /> ! SFO31604.DA <br /> QTY Unit $/unit COST COMMENT <br /> SITEWORK <br /> .Site Preparation 1 LS 5,000 5,000 Allowance <br /> EQUIPMENT <br /> Flow EQ Tank 1 LS $6,000 $6, 000 3,000 gal tank <br /> Influent Pumps 4 each $1, 500 $6, 000 <br /> i . Air Stripping System 2 each $15,000 $30,000 <br /> Acid Addition System 1 LS $4,000 $4, 000 <br /> Caustic Add. System 1 LS $4,000 $4, 000 <br /> j Blowers 2 each $2,000 $4, 000 <br /> Effluent Pumps 2 each $1,500 $3, 000 <br /> Catalytic Ox Unit 1 LS $65, 000 $65,000 <br /> Subtotal = 127,000 <br /> Unquantified Items (5% of subtotal) 6,350 <br /> Freight Allowance (10% of subtotal) 12,700 <br /> Installation Allowance (15% of subtotal) 19, 050 <br /> Subtotal = 165,100 <br /> j MECHANICAL ( 15% of Equipment Total ) 24,765 <br /> ELECTRICAL & I&C ( 15% of Equipment Total ) 24,765 <br /> CONSTRUCTION COST SUBTOTAL 214,630 <br /> Contingency ( 25% of CCS ) 53, 658 <br /> TOTAL CONSTRUCTION COST 268,288 <br /> Mob,Demob,Bonding, & Insurance ( 8% of TCC ) 21, 463 <br /> Permitting & Legal ( 5% of TCC ) 13, 414 <br /> Services During Construction ( 5% of TCC ) 13, 414 <br /> Start-Up Costs ( 5% of TCC ) ----13,414 <br /> TOTAL IMPLEMENTATION COST 329, 993 <br /> Engineering Design Costs ( 12% of TIC ) 39, 599 <br /> TOTAL CAPITAL COST 370,000 <br /> i <br /> Page 1 <br />