Laserfiche WebLink
Figure 2 <br /> Project Schedule <br /> Assess Extent of Affected Groundwater Adjacent to Pipeline Block Valve <br /> Stockton Junction at Intersection of Inland Drive and Jacobs Road <br /> ID Task Name Duration Start Finish Jun Jul AugSep Oct Nov Dec <br /> 1 RWQCB Review 20 days Mon 07/01/02 Fri 07/26/02 <br /> 2 0 Receive Work Plan 0 days Mon 07/01/02 Mon 07/01/02 07/01 <br /> 3 Review Work Plan 20 days Mon 07/01/02 Fri 07/26/02 <br /> 4 Approve Work Plan 0 days Fri 07/26/02 Fri 07/26/02 07/26 <br /> 5 Prepare for Field Investigations 50 days Mon 07/29/02 Fri 10/04/02 <br /> 6 Obtain Access Agreement 40 days Mon 07/29/02 Fri 09/20/02 <br /> 7 Other Preparation Activities 10 days Mon 09/23/02 Fri 10/04/02 <br /> 8 Field Work 20 days Fri 10/04/02 Fri 11/01/02 <br /> 9 Begin Field Work 0 days Fri 10/04/02 Fri 10/04/02 10/04 <br /> 10 Day 1 -Install Piezometers,Collate Grab GW Samples 1 day Mon 10/07/02 Mon 10/07/02 �j 1 <br /> 11 Day 2-Survey and Assess GW Flow Direction 1 day Tue 10/08/02 Tue 10/08/02 1♦ <br /> 12 Laboratory Analysis of Samples 7 days Wed 10/09/02 Thu 10/17/02 <br /> 13 Day 3-Collect Additional Grab GW Samples 1 day Fri 10/18/02 Fri 10/18/02 <br /> 14 Laboratory Analysis of Samples 10 days Mon 10/21/02 Fri 11/01/02 <br /> 15 Prepare Report 25 days Mon 11/04/02 Fri 12/06/02 <br /> 16 Prepare Report 25 days Mon 11/04/02 Fri 12/06/02 <br /> 17 Submit Report to RWQCB 0 days Fri 12/06/02 Fri 12/06/02 . 12/0 t <br /> Task Summary Rolled Up Progress <br /> Project:Stockton_Junction_Schedule Split Rolled Up Task External Tasks <br /> Date:Thu 06/27/02 Progress Rolled Up Split Project Summary <br /> Milestone ♦ Rolled Up Milestone 0 <br /> Page 1 <br />