6 ' <br /> J <br /> Kennedy/Jenks Consultants <br /> ff <br /> Section 6: Implementation Schedule <br /> It is anticipated that the Work Plan will be implemented according to the following schedule, <br /> depending upon the availability of drilling subcontractors and San Joaquin County inspectors: <br /> • 15 May 2009 — Submit Work Plan to the CRWQCB. <br /> • 29 May 2009 — Receive approval or comments from the CRWQCB. Submit well <br /> installation permit application. Q <br /> • 15 June 2009 — Initiate drilling and monitoring well installation activities. <br /> • 19 June 2009 — Develop monitoring wells. <br /> • 22 June 2009 — Collect groundwater samples. n <br /> • 6 July 2009 — Receive analytical results of groundwater samples. lUl <br /> • 10 August 2009 — Submit Report to the CRWQCB. <br /> 1i <br /> 1 <br /> R <br /> k <br /> W <br /> Page 14 Monitoring Well Installation Work Plan <br /> Sutter Home Winery, Lodi, California <br /> g Yss-gmup�dmin4ob108W865005.Oi_suwWmeWgrpofth install ask pintleAdOC <br />