Laserfiche WebLink
5.0 Schedule <br /> IT is prepared to initiate the utility survey on May 22, 2002 and the drilling on May 29, 2002 <br /> pending Caltrans and Regulatory approval of the Workplan and health and safety plan. It is <br /> anticipated that the utility survey can be completed in approximately one day and the drilling can <br /> be completed in approximately two days. Samples will be submitted to the laboratory within 48 <br /> hours of collection. The laboratory analyses will be conducted on a normal turn around basis. <br /> Following receipt of all analytical data, it is anticipated that a draft report documenting the <br /> findings of the investigation will be submitted 10 working days after the completion of the work. <br /> SAC/DP-N.IrmiejpllProjectsl8318370841wp&hsplStockion&Patterson wp.doc 5-1 <br /> 513102 <br />