Laserfiche WebLink
I KLE/NFELOER <br /> —/Bright People,Right Solutions. <br /> 3 SCHEDULE <br /> The estimated schedule for the proposed scope of work is approximately 30 working <br /> days. The schedule is subject to actual regulatory review time. <br /> I- <br /> Time Frame Description of Task <br /> 2 weeks* Work plan review and approval* <br /> 1 day Soil Sampling <br /> 1-2 weeks** Laboratory Analyses** <br /> 2 weeks Report <br /> Kleinfelder has no control over the time required to have the work plan reviewed and approved. This time frame should be <br /> considered an estimate only. <br /> "Laboratory analyses of soil samples will be performed using a standard 7-10 processing timeframe. <br /> Report preparation will begin upon receipt of all analytical data from the laboratory. As <br /> specified herein <br /> 112884.1/STO10R347 Page 4 of 5 August 30, 2010 <br /> Copyright 2010 Kleinfelder <br />