. Thrifty Oil Co <br /> Station # 172 <br /> 8.2 SCHEDULE <br /> This time line is for the installation and start-up of an approved remediation system Thrifty presents <br /> this tentative schedule based upon the approval of this Corrective Action Plan(CAP) Once Thrifty <br /> receives approval of this CAP,permit(s) will be requested from the San Joaquin Valley Unified Air <br /> Pollution Control District (APCD), Central Valley Regional Water Quality Control Board <br /> (CVRWQCB), and San Joaquin electrical utilities It is anticipated that the APCD permit will be <br /> obtained in approximately eight weeks, the NPDES permits will be obtained in approximately 30 <br /> weeks, and the electrical permits in approximately four weeks Acquisition and installation of the <br /> unit will take approximately four weeks subsequent to permit acquisition So once the CAP is <br /> approved the system should be operating within 34 weeks This schedule is subject to change due <br /> to unavoidable circumstances <br /> 11 <br />