6.0 IMPLEMENTATION SCHEDULE <br /> A post-approval implementation schedule was prepared assuming Alternative 1 is chosen for <br /> execution. Site-specific groundwater monitoring was not considered because it is an estab- <br /> lished task. Day 0 is assumed to be the regulatory approval date. The proposed schedule is <br /> shown below. <br /> Task Days <br /> Development of Comprehensive Monitoring and Reporting Program 30 <br /> Development of Institutional Controls 90 <br /> Implementation of Institutional Controls 120 <br /> General Recommendations As Appropriate <br /> 3201357B/CAPREV I 16 June 29, 1995 <br />