Laserfiche WebLink
1 <br /> • A final report will be prepared by Western Oil & Spreading after all field work is <br /> ' completed The target completion date of the Acampo plant site sod remediation is <br /> December 30, 2005 Completion date will be dependent upon weather delays, actual <br /> quantity requiring excavation and disposal offsite versus onsite treatment option chosen <br /> after soil is excavated and characterization is finite <br /> 42 Budget and Cost Controls <br /> ' Budget and Cost Control information will be developed and maintained internally by <br /> WO&S All cost information is considered to be confidential <br /> 4.3 Remediation Goals <br /> Soil will be restored to a cleanliness standard of 400 ppm or 400mglkg TPH-D prior to <br /> the remediated material being returned to the excavation zone (unless findings from <br /> future risk analysis supports a different, mutually agreed to, standard ) <br /> 1 <br /> 4-4 <br />