20 January 2000 <br /> AGE-NC Project No 95-0173 <br /> Page 11 of 14 <br /> hollow stem augers Each SVE well will utilize fifteen feet of slotted well casing (0 020-inch screen <br /> size) from 5 to 20 feet bsg A #3 Lonestar Lapis Luster sand will be poured down the annulus <br /> between the well casing and the inner wall of the hollow stem auger The filter pack will be placed <br /> adjacent to the screen from the bottom of the boring to a point approximately 2 feet above the top <br /> of the screen A two foot interval of bentonite pellets (annular seal) will be placed above the filter <br /> pack Portland cement will be utilized to grout from the annular seal to surface grade A SVE well <br /> construction diagram is depicted in Figure 5 <br /> 4 2 2 _Soil Vapor Extraction Piping System <br /> A network of two-inch diameter, schedule 40 PVC piping will be installed in 6-inch wide by 12-inch <br /> deep trenches at the site The PVC piping will be routed from each SVE well head to a vapor dropout <br /> drum, the vapor dropout drum will be directly connected to the VES A PVC ball valve will be <br /> installed at each SVE well head so that vapors can be drawn from each well independently A plan <br /> of the proposed piping system and-enclosed VES unit location are depicted in Figure 4 <br /> The location of the VES unit is proposed near the southwest corner at the site (Figure 5) This <br /> proposed location of the VES unit will allow neighboring properties to conduct their day to day <br /> business without interference from the operation of the VES unit The VES unit will be secured by <br /> a chain-linked, gated enclosure with measurements 15 feet wide by 20 feet long and six feet in <br /> height <br /> 4 2 3 Soil Vapor Extraction Supplemental Fuel <br /> Supplemental fuel (propane gas) is proposed for the operation of the selected VES unit An <br /> automatic air dilution module adjusts for the optimal combustion parameters by adding oxygen <br /> and/or supplemental fuel Propane is the only fuel readily available to the site A dedicated propane <br /> system and meter will be installed by representatives of AGE that would connect directly to the VES <br /> unit <br /> 4 2 4 Soil Vapor Extraction Monitoring Activities <br /> The VES unit will be monitored weekly using a photo-Ionization detector(PID) and Dwyer DS-200 <br /> flow sensor to ensure optimal destruction of recovered hydrocarbon vapors, and to monitor cleanup <br /> progress The PID readings will be recorded from the influent end of the VES unit, and recorded <br /> before and after catalytic destruction Operational parameters (air flow, combustion temperature, <br /> Advanced GcoEnvlronincoal,Inc <br />