During first quarter 2005, Stratus prepared and submitted an ATC application to SJVAPCD for the new <br /> 500 cfm Solleco thermal oxidizer Stratus retained an electrical contractor to make electrical connections <br /> between the existing electrical distribution panel and the control panel of newly installed 500 cfm thermal <br /> oxidizer This work was completed during March 2005 Stratus also retained a propane vendor to install a <br /> 500-gallon propane tank and provide propane service required for the operation of thermal oxidizer The <br /> start-up of the 500-cfm thermal oxidizer is currently scheduled for the third week of April 2005 <br /> ATTACHMENTS <br /> • Table 1 Product Monitoring and Removal Summary <br /> • Table 2 Groundwater Level Data <br /> • Table 3 Groundwater Analytical Summary <br /> • Table 4 Groundwater Analytical Results for Oxygenates and Additional Compounds <br /> • Table 5 Summary of Wells <br /> • Figure 1 Site Location Map <br /> • Figure 2 Site Plan <br /> • Figure 3 Groundwater Elevation Contour Map, Upper Water Bearing Zone (1st Quarter 2005} <br /> • Figure 4 Groundwater Elevation Contour Map, Lower Water Bearing Zone (1st Quarter 2005) <br /> • Figure 5 Groundwater Analytical Summary (First Quarter 2005) <br /> • Figure 6 Influent GRO and Cumulative GRO Mass Removed Over Time—SVE Unit 1 <br /> • Figure 7 Influent GRO and Cumulative GRO Mass Removed Over Time—SVE Unit 2 <br /> • Appendix A Field Data Sheets <br /> • Appendix B Sampling and Analysis Procedures <br /> • Appendix C Certified Analytical Reports with Chain-of-Custody Documentation and EDF <br /> Verification <br /> • Appendix D Performance and Operation Summary of King, Buck, &Associates SVE Systems <br /> K 1Bp-Arco for URS\6100\Quarteriy\2005\Arco_6100_IQ05 doc STRATUS <br />