• <br /> • <br /> • F. SCHEDULE FOR COMPLETION OF WORK <br /> • <br /> • The following schedule for installation of the monitoring wells is proposed: <br /> Action Target Completion Date <br /> • Submit Workplan to Regional Board 14 March 2005 <br /> • Regional Board Approval of Workplan 14 April 2005 <br /> • Retention of Drilling Contractor and Coordination of 14 June 2005 <br /> • Permits and Utility Clearances <br /> • Monitoring Well Installation and Development and 14 August 2005 <br /> • Groundwater Sample Collection <br /> • Submit Report of Results to Regional Board 14 September 2005 <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • <br /> • Riverbank WWTP Workplan Nolte Associates,Inc. <br /> • March 2005 7 \\SmO\project\SA1542\mon_well\new\gwmwiwp\wp.doc <br /> • <br />