Laserfiche WebLink
SECTION 7 <br /> PROJECT SCHEDULE <br /> The RI planning, implementation, and reporting stages are expected to <br /> take approximately 417 days, as summarized in Table 4. <br /> Table 4 <br /> Project Schedule <br /> Number <br /> Activity of Days <br /> Draft RI Workplan Preparation 45 <br /> Navy Review 14 <br /> Final RI Workplan Preparation 15 <br /> Regulatory Board Review 60 <br /> Field Work/Draft RI Report Preparation 90 <br /> Navy Review of Draft RI Report 14 <br /> Pre-final RI Report Preparation 15 <br /> Regulatory Agency Review 45 <br /> Draft FS/CAP Preparation 30 <br /> Navy Review 14 <br /> Pre-final FS/CAP Preparation 15 <br /> Regulatory Agency Review 45 <br /> Final RI/FS/CAP Preparation 15 <br /> Total Project Duration 417 <br /> 7-1 <br />