GEOMATRIX <br /> 6.0 PRELIMINARY SCHEDULE <br /> Simplot and Geomatrix have developed the following preliminary schedule for implementation <br /> of the EMP previously described. The EMP will be initiated within approximately 30 days of <br /> approval of this work plan and can be implemented in accordance with the following schedule, <br /> assuming no unanticipated conditions arise and subcontractors are readily available: <br /> TASK INITIATE' COMPLETE' <br /> Phase I Evaluation Monitoring Program 30 120 <br /> (If Necessary,Phase II Evaluation Monitoring Program) (120) (180) <br /> Engineering Feasibility Study 120(180) 210(270) <br /> Detection Monitoring Program 120(180) 210(270) <br /> Corrective Action Program(Report of Waste Discharge) 210(270) 300(360) <br /> Approximate number of days from RWQCB approval of this work plan. Values in(parenthesis)assume that <br /> Phase II evaluation monitoring will be required. <br /> 1:\6000&\6741.000\P.rchive\6741-13.doc 12 <br />