Work Plan to Install Compliance Groundwater Monitoring Wells,Musco <br /> ' Family Olive Company Tracy Cal'rfornia <br /> A minimum of 48 hours following development,groundwater samples will be collected from the newly <br /> installed monitoring wells using sampling techniques currently used for the Musco facility groundwater <br /> monitoring program in support of WDR Order No. R5-2005-0024(As described in the associated <br /> ' groundwater monitoring reports). Depth to groundwater will be measured in each well and water- <br /> quality parameters(pH,conductivity, ORP, DO,and temperature)will also be monitored during purging. <br /> These depths and field monitoring parameters will be logged onto water level and water quality logs <br /> ' (Attachment 1).The groundwater samples will be labeled, logged on chain-of-custody forms,and placed <br /> in an ice-chilled cooler for transport to the laboratory for the same analysis required by WDR Order No. <br /> ' RS-2005-0024. <br /> Investigation Derived Waste <br /> ' Investigation derived waste water and soil generated during this investigation will be disposed of on the <br /> ground in the vicinity of the soil boring,as completed during previous monitoring well installations at <br /> ' the Musco facility. <br /> Anticipated Project Schedule <br /> ' The anticipated schedule for the project is provided below: <br /> • October 30, 2013:Submittal of Work Plan via email to the RWQCB. <br /> ' November 8,2013:Anticipated approval of Work Plan by RWQCB. <br /> • November 13, 2013: Initiate drilling activities. <br /> ' • November 22, 2013:Anticipate drilling activities to be completed. <br /> • November 25, 2013: Initiate well development activities. <br /> • November 27,2013:Complete well development activities. <br /> ' • December 9, 2013: Initiate first groundwater monitoring and sampling event. <br /> Please note that this schedule is dependent upon regulatory approval, contractor availability and <br /> ' weather conditions.Any changes to this anticipated schedule will be communicated to the RWQCB as <br /> the project is implemented. <br /> If you have any questions with regard to the procedures described in this work plan, please do not <br /> hesitate to give me a call at(510)326-1473. <br /> ' Sincerely, <br /> For Terraphase Engineering Inc. <br /> Andrew Romolo, P.G. (8110) <br /> Vice President and Principal Geologist <br /> ' Terraphase Engineering Inc. Page 5 of 6 <br /> 1 <br />