a <br /> SCHEDULE <br /> LIST OF TASKS AND ESTIMATED TIME TO COMPLETE <br /> TASK 1 - PREFIELD ACTIVITIES 2 WEEKS <br /> TASK 2 - INSTALL VAPOR'CONDUIT TO EXTRACTION WELLS 1 WEEK <br /> TASK 3 - DESIGN OF THE VES 1 WEEK <br /> TASK 4 - PERMITTING OF THE VES 1 WEEK <br /> TASK 5 - INSTALLATION OF THE VES 1 WEEK <br /> TASK 6 - INITIAL STARTUP OF VES 2 WEEKS <br /> TASK 7 - MONITORING, MAINTENANCE, AND OPERATION OF VES 52 WEEKS <br /> TASK 8 - MANAGEMENT 54 WEEKS <br /> TASK 9 - REPORTING 12 WEEKS <br /> I <br /> TOTAL ESTIMATED TIME TO COMPLETE PROJECT 54 WEEKS <br /> i <br /> i <br /> I <br /> i <br /> I <br /> VAPOR EXTRACTION TECHNOLOGY <br /> -i i <br />