Laserfiche WebLink
7rdrITOR <br /> A-4 %w.lf <br /> ENGREEM0 INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Daily Field Report Sequence Number: <br /> Forward Landfill 021605.03 75 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Manteca, Ca Butch Stefan Forward,Inc. December 2,2003 Tuesday <br /> General Contractor: Liner Contractor: Project Engineer: <br /> Sukut Construction GSE San Beta Lewis <br /> General Foreman: Liner Superintendent: Others: <br /> Tim Sues Ayre Khounmouang Lochlin Caffe <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native, stockpiled, light brown silty Clay Cool, foggy(AM) Ken Davila <br /> clear M and bree <br /> Equipment on site: <br /> 1-16G blade, 1-ski loader 1-backhoe <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I arrived on site and met with the GSE foreman to discuss the work schedule for today. They continued <br /> extrusion welding of the cross seam patches and the tie-in seams on the southern half of the FU-03 cell <br /> floor. Twelve-ounce(12oz)geotextile was rolled up in the northeastern quadrant of the cell floor in the <br /> afternoon. Destructive samples were cut and obtained up to DS47,which completed the required sampling <br /> frequency. Since sample number DS-33 had previously failed,two(2)more samples were obtained. These <br /> were taken ten feet(10')on either side of the DS-33 location and were marked as DS-33A and DS-33B. <br /> The area between these samples and the seam before another passing destructive sample for that machine <br /> was extrusion welded. <br /> Forward personnel swept rainwater off the whole of the cell floor throughout the day. This was to assist <br /> the leak testing firm. <br /> Sukut Construction imported baserock and placed and graded the access road into the cell. Sump pipes for <br /> the leachate pond and cell were welded together on the upper deck. The foreman stated that another sample <br /> of the coarse drain rock would be delivered by tomorrow(12-3-03)or Thursday(12-4-03). <br /> Leak Location Services,Inc. (LLSI)personnel were on site to set up for leak testing. Their foreman stated <br /> that they would be back on site at 6:00 pm to begin testing. In the early evening, LLSI returned to the site <br /> and began set up and leak testing. By 9:30 pm the northern half of the cell was complete. The maximum <br /> area which could be tested was determined by the hose length and grounding wire. The foreman stated that <br /> they would return in the morning and set up on the northeast corner of the cell to complete cell testing. <br /> AWL <br /> Prepared By: Reviewed By: <br /> 4/23/03,Rev. 0 1 of 1 <br /> r-, <br />