Post-Closure Cost Estimate <br /> The 2002 post-closure cost estimate was updated to reflect 2008 costs and includes <br /> the newly required additional back-up cost information under 27 CCR. It was <br /> determined that no changes to the post-closure cost estimate are necessary to <br /> implement the staged closure of the FL. The 2008 post-closure cost estimate is <br /> included herein as Table 4. Once a given stage is completed and the area is certified <br /> as closed, then post-closure maintenance activities consistent with the 2002 PCPCMP <br /> and Amendments will commence. Post-closure activities will be conducted for a <br /> minimum of 30 years or until the operator can demonstrate that the site no longer <br /> poses a threat to the public and the environment. <br /> 12 <br /> Forward Landfill-PCPCMP Amendment <br /> (Z:\PROJECTS\Al lied Waste\JN81013 5 yr Review Plan\PCPCMP Amend 3 July 08\Clos Amend 3 Final.doc; <br /> Amendment No.3:7/1/2008) <br />