3.13 CLOSURE IMPLEMENTATION SCHEDULE <br /> 3.13.1 CLOSURE PROCESS <br /> As discussed in Section 1.5, Stage IA of the Forward Landfill will be closed in <br /> Summer 2005. Stage IA closure construction will begin with mobilization of <br /> equipment and materials. The type of equipment and required personnel <br /> expected to be utilized during closure construction includes but is not limited <br /> to, the following: <br /> • Equipment <br /> - Scrapers <br /> - Dozers <br /> Loaders <br /> - Compactors <br /> Trucks <br /> - Soil Screening Equipment <br /> - Motor Grader <br /> - Water Truck <br /> • Personnel <br /> Construction Manager <br /> - Field Inspector(s) <br /> - Engineer(s) <br /> - Geotechnical Engineer/Geologist <br /> - Geotechnical Technician(s) <br /> - Labor Crews <br /> - Equipment Operators <br /> - Surveyors <br /> Mechanics <br /> 3.13.2 CONSTRUCTION SCHEDULE <br /> The AVSL closure construction schedule includes the following tasks <br /> conducted over the corresponding time lines: <br /> Equipment Mobilization 2 weeks <br /> Interim/Foundation Layer Preliminary Grading 1-1/2 weeks <br /> • Placement of Monolithic Cover Layer 8 weeks <br /> Drainage Control Systems Construction 5 weeks <br /> • Survey/Settlement Monument Installation 1 week <br /> ® French Drain Leachate Seep Collector Installation 2 weeks <br /> Forward Landfill PFCPCMP 3-17 <br /> Z:\PROJECTS\Allied Waste\Forward\Reference Files Prior JTD\June 05 Stage IA Partial FCPCMP\FL-sec3.doc:6/16/2008 <br />