• <br />• <br />J <br />Geo-LoqkASSOCIATE <br />CQA DAILY SUMMARY REPORT #044 <br />REPUBLIC SERVICES FORWARD LANDFILL, FU -13 <br />Location: Manteca, CA Owner: Republic Services <br />CQA Consultant: Geologic Associates Contractors: Guinn Construction <br />Prepared by: Jose Armenta (GLA) Comanco Environmental Corp. <br />Submitted to: Scott Purdy (GLA) <br />Project #: 2013-AO55 <br />Report No.: 044 Report Date: Monday July 15, 2013 <br />Weather: AM: 64°F Clear <br />Guinn Construction Activities: <br />Onsite: 05:00 - 17:30 Hrs <br />PM: 94°F Clear <br />• The Contractor continued transferring drainage gravel material to the site; the drainage gravel material was <br />stockpiled along the NE side outside of FLI-13. <br />The Contractor started moisture conditioning of clay material for use during the liner anchor trench backfill, <br />clay plug. <br />• The Contractor continued moisture conditioning of access roads and adjacent areas. <br />• Personnel: (1) Operator <br />Equipment: (1) Water truck. <br />Comanco Lining Activities: 0500-1630 hrs <br />• Comanco continued installation of the single sided geocomposite over the completed HDPE liner on the north <br />4:1 slope. <br />• The geocomposite was installed from the top of the slope inside the liner anchor trench and onto the slope <br />bench. The net component of the geocomposite panels was overlapped a minimum of 3 -inches and fastened <br />using white plastic ties at 3-4 foot intervals. The textile component of the Geocomposite was sewn using the <br />double stitching sewing method. <br />• The Contractor used air blowers over the surface of the HDPE liner prior to the installation of the <br />Geocomposite to remove accumulated dust and debris. <br />• All geocomposite material installed today was secured with ballast sand bags at the end of the work shift. <br />• Personnel: 12 Equipment: (1) Fork Lift, (1) equipment trailer, (1) Van, (3) Trucks <br />PAGE 1 OF 2 <br />