Laserfiche WebLink
• <br />Geo-LoqkA S S O C I AT E S <br />CQA DAILY SUMMARY REPORT #065 <br />REPUBLIC SERVICES FORWARD LANDFILL, FU -13 <br />Location: <br />Manteca, CA Owner: <br />Republic Services <br />CQA Consultant: <br />Geologic Associates Contractors: <br />Guinn Construction <br />Prepared by: <br />Jose Armenta (GLA) <br />Comanco Environmental Corp. <br />Submitted to: <br />Scott Purdy (GLA) <br />Project #: <br />2013-AO55 <br />Report No.: 065 <br />Report Date: Friday August 09, 2013 <br />Onsite: 06:00 - 16:30 Hrs <br />Weather: AM: 55°F <br />Clear <br />PM: 84°F Clear <br />Guinn Construction Activities: <br />• The Contractor completed placement of the granular drainage gravel in the upper deck area. The Contractor <br />used a wide track LGP D6R Cat Dozer equipped with GPS to spread the granular drainage gravel in a <br />continuous 12 -inch lift. <br />• The Contractor completed placement of the filter fabric over the completed granular drainage layer. The <br />Contractor installed and welded the 8 -oz geotextile panels using the hot-air seaming method using two (2) <br />leister heat guns. <br />• The Contractor completed placement of the 12 -inch operations soil layer over the completed filter fabric <br />layer in the upper deck. The Contractor used a 760 Cat rock truck to transfer the drainage gravel and the soil <br />materials; a D6 Cat dozer equipped with GPS was used to spread the granular and soil materials to the <br />required thickness. <br />• The Contractor built soil access ramp at half of south side of Cell floor. <br />• The Contractor completed soil placement along the east liner termination berm. <br />Personnel: (4) Operators, (1) Supervisor, (1) Grade checker, (3) Laborers. <br />Equipment: (1) Water truck, (2) 637 Cat Scrapers, (1) D6N Cat Dozer, (1) D611 LGP Cat Dozer, (1) 966 Cat <br />Loader, (1) 14H Cat Motor grader, (1) Cat Fork Lift, (1) Generator, (2) Leister Heat Guns. <br />CQA (GLA) Activities: Field Personnel (1) <br />• CQA personnel performed continuous monitoring of all construction activities ensuring conformance with the <br />project specifications. <br />• CQA personnel monitored the placement of the drainage gravel material at all times ensuring that proper <br />procedures were used to prevent damage to the underlying synthetic liner. <br />PAGE 1 OF 2 <br />