TABLE
<br /> FORWARD LANDFILL
<br /> ANNUAL POST-CLOSURE MAINTENANCE AND MONITORING
<br /> COST ESTIMATE SUMMARY (2013)
<br /> Item Unit Price Total
<br /> No. Description Quantity
<br /> T-
<br /> 11 SITE SECURITY(10)
<br /> System Maintenance/Repair
<br /> Inspection 20 hrs 65 per/hr $1,300
<br /> Labor 20 hrs 65 per/hr $1,300
<br /> Equipment 8 hrs 111 $888
<br /> Materials 1 LS 2,500 $1,000
<br /> Subtotal $4,488
<br /> TOTAL ANNUAL POST-CLOSURE MAINTENANCE AND MONITORING COSTS $446,543
<br /> TOTAL 30-YEAR POST-CLOSURE MAINTENANCE AND MONITORING COSTS $13,396,290
<br /> Notes:
<br /> See Attachment No.1 for labor and equipment rates per hour utilized in the development of Post-Closure Cost Estimate. The material unit prices
<br /> from Table 3 were utilized to develop material costs for Items 6,7,and 10. Quantities were based on assumptions made by SWT Engineering
<br /> based on our experience with other landfills. Labor and rates were obtained from the State of California Industrial Relations;prevailing wage
<br /> schedule pursuant to California Labor Code Part 7,Chapter 1,Article 2,Sections 1770,1773,and 1773.1. Equipment rental rates were
<br /> obtained from the CalTrans Labor Surcharge and Equipment Rental Rates effective through March 31,2012. SWT was also provided current
<br /> invoices/costs for all environmental services currently being conducted by Forward Landfill for consideration and use in developing this post-
<br /> closure cost estimate.
<br /> (1)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,gas meter,tools,miscellaneous
<br /> items,Backhoe(CAT 4466)and materials to replace up to 4 collection wells per year to average depth of 150 feet and one LFG migration
<br /> monitoring probe to the depth of refuse annually.
<br /> Cost assumption for system monitoring/testing includes labor(Sr.Engineering Technician),gas meter,sampling materials,pick-up truck,flare
<br /> source testing,laboratory,management by Sr.Engineer(based on a review of current rates for professional consulting firms)and reporting per
<br /> regulations.
<br /> (2)Cost assumption for system maintenance/repair includes labor(Sr.Engineering Technician)equipment(pick-up truck,tools,pump,etc.)and
<br /> replacement of one monitoring well every two years based on the following:$9,000 for similar well 50-feet deep including permit at$500 and
<br /> geologging at$2,000.
<br /> Cost assumptions for system monitoring includes labor(Sr.Engineering Technician),pick-up truck,sampling equipment,laboratory,management
<br /> by a Sr.Geologist(based on a review of current rates for professional consulting firms),analysis by a geologist and preparation of necessary
<br /> reports for the RWQCB.
<br /> (3)Cost assumptions for system operation and maintenance include labor(Sr.Engineering Technician),a pick-up truck,tools,parts,electricity,
<br /> and filter mediums.
<br /> (4)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,tools,miscellaneous items,and
<br /> materials.
<br /> Cost assumption for system monitoring/testing includes labor(Sr.Engineering Technician),gas meter,sampling materials,pick-up truck,
<br /> laboratory,management by Sr.Engineer(based on a review of current rates for professional consulting firms),analysis by a geologist,and
<br /> reporting per regulations.
<br /> (5)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,tools,miscellaneous items,and
<br /> materials.
<br /> Cost assumption for system monitoring/testing includes labor(Sr.Engineering Technician),sampling materials,pick-up truck,laboratory,
<br /> management by Sr.Engineer(based on a review of current rates for professional consulting firms),analysis by a geologist,and reporting per
<br /> regulations.
<br /> (6)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician,heavy equipment operators),a pick-up truck,
<br /> tools,miscellaneous items,loader(CAT 966G),dozer(CAT D8-N),dump truck(22 tons),a 3,000-gallon water truck,and materials to replace 1
<br /> acre each of lined and unlined final cover.
<br /> (7)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,tools,miscellaneous items,and
<br /> materials to provide rodent control and hydroseeding and add soil amendments to 1 acre of final cover each year.
<br /> (8)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,tools,miscellaneous items,
<br /> Motorgrader(CAT 14-H),and materials to repair 100 If of access road each year.
<br /> (9)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,high-pressure sprayer,tools,
<br /> Backhoe(CAT 4468)and materials to replace up to 150 If of perimeter channel and 100 If of 24"HDPE downdrain pipe each year.
<br /> (10)Cost assumptions for system maintenance/repair include labor(Sr.Engineering Technician),a pick-up truck,backhoe,tools,and materials
<br /> to replace up to 100 If of fencing each year.
<br /> Z:\PROJECTS\Allied Waste\Fo rward\Five Year Permit Rvw 2013\JTD-5 Yr PR 2013\,Appendicesypp A-PCPCMP 2013\Tables\Table 4-Post Closure Cost Estimate-
<br /> 2013;Amend.No.4:5/28/2013 Page 3 of 3