Laserfiche WebLink
WASTE DISCHARGE REQUIREMENTS ORDER NO. R5-2014-0006 -37- <br /> FORWARD INC.AND REPUBLIC SERVICES INC. <br /> FORWARD CLASS 11 LANDFILL <br /> SAN JOAQUIN COUNTY <br /> Task Compliance Date <br /> A. Construction Plans <br /> Submit construction and design plans for review and 90 days prior to <br /> approval. (see all Construction Specifications in proposed construction <br /> Section D, above and Section F of the SPRRs.) <br /> B. Construction Report <br /> Submit a construction report for review and approval 60 days prior to <br /> upon completion demonstrating construction was in proposed discharge <br /> accordance with approved construction plans (see <br /> Standard Construction Specification F.27 in the <br /> SPRRs). <br /> C. Final Closure Plans <br /> Submit a final or partial final closure and post-closure Two years prior to <br /> maintenance plan, design plans, and CQA plan for closure <br /> review and approval (see all Closure and Post- <br /> Closure Specifications in Section E, above and <br /> Section G of the SPRRs). <br /> D. Unsaturated Zone Monitoring System <br /> Submit a report that reviews the status of the 1 June 2014 <br /> unsaturated zone monitoring system. The report <br /> should document those monitoring points that need <br /> repair or replacement, consider the need for <br /> additional monitoring points and should establish a <br /> time schedule to completely restore the monitoring <br /> system. <br /> E. Closure and Postclosure Maintenance Plan <br /> Submit a revised Closure and Postclosure 1 June 2014 <br /> Maintenance Plan with closure stages dates. The <br /> revised Plan must include revised cost estimates for <br /> Closure Financial Assurances. <br /> F. Update Corrective Financial Assurance Cost <br /> Estimate <br />