1 <br /> CORRAL HOLL 0 W SANITARLANDFILL <br /> WORKPLAN <br /> Damage Work Required Completion of Corrective <br /> Action <br /> Eroded ditch on a portion of Remove any garbage or April 10, 1998 <br /> the eastern boundary exposed debris existing in the ditch. <br /> a garbage/soil mixture. <br /> Eroded ditch on a portion of Fill ditch with dirt/rock to May 15, 1998 <br /> the eastern boundary of the restore to pre-winter <br /> landfill. condition. Add rock and/or <br /> other erosion control <br /> measures. <br /> Broken chain-link perimeter Hire fence company to reset May 15, 1998 <br /> fencing on southeastern posts and restore 6'chain- <br /> portion of the property. link fence. <br /> Repair washed out perimeter Scrape away damaged June 12, 1998 <br /> roadway in the area of the portions of roadway,fill back <br /> broken fence. to grade with rock, and re-oil. <br /> Repair miscellaneous minor Fill and compact with June 19, 1998 <br /> erosion. soil/rock, install drainage <br /> pipes inecessa <br />