Laserfiche WebLink
CORRAL HOLLOW SANITARY LANDFILL <br /> LANDFILL GAS CONTROL SYSTEM <br /> WORK LAN <br /> APPROXIMATE APPROXIMATE <br /> TASK DATE BEGIN DATE ENDING <br /> Begin pre-qualification of <br /> environmental engineering firms March 30, 1998 May 15, 1998 <br /> Issue Requests for Proposals to the <br /> top five qualified firms and review May 29, 1998 July 15, 1998 <br /> proposals and interview consultants <br /> Process an agreement with the <br /> successful consultant July 15, 1998 September 15, 1998 <br /> Prepare environmental documents July 15, 1998 November 15, 1998 <br /> Consultant prepares preliminary design November 15, 1998 March 30, 1999 <br /> County reviews preliminary design March 30, 1999 April 30, 1999 <br /> Consultant prepares final design <br /> and specifications April 30, 1999 June 15, 1999 <br /> Bid and award project June 15, 1999 July 30, 1999 <br /> Construction July 30, 1999 December 30, 1999 <br />