4.0 CLOSURE CAP EXTENSION IMPLEMENTATION SCHEDULE <br /> TABLE 1 <br /> CLOSURE CAP EXTENSION SCHEDULE <br /> CORRAL HOLLOW SANTIARY LANDFILL <br /> ITEM TENTATIVE <br /> COMPLETION DATE <br /> 1 Comments and approval Review by regulatory October 24, 2011 <br /> agencies received <br /> 2 Shaw Incorporates regulatory agency comments November 14, 2011 <br /> 3 Review and revisions by Public Works Design December 12, 2011 <br /> Division complete <br /> 4 Submit package to Board of Supervisors January 9, 2012 <br /> 5 Bid advertised - start of bid period (see note) January 31, 2012 <br /> AdEL 6 Bid Opening: March 1, 2012 <br /> IF <br /> 7 Contract Awarded March 20, 2012 <br /> 8 Begin Construction (start of new fiscal year) July 9, 2012 <br /> 9 Construction complete September 3, 2012 <br /> 5.0 STRUCTURE REMOVAL <br /> No structure in the landfill property will be removed for this project. <br /> 6.0 DECOMMISSIONING OF ENVIRONMENTAL CONTROLS <br /> No environmental controls will be decommissioned in this project. <br /> 7.0 SITE SECURITY <br /> Signs stating the closure of CHSL are still in place at the site. No additional signs will be <br /> placed for the closure cap extension project. <br /> Closure Plan Revised Addendum San Joaquin County <br /> Corral Hollow Sanitary Landfill 5 Department of Public Works <br /> October 6.2011 Solid Waste Division <br />