1 • Groundwater Monitor Well Installation Work Plan <br /> City of Manteca Wastewater Treatment Facility <br /> ' 7.0 SCHEDULE Page 4 <br /> We anticipate that the field activities described can be completed and the Monitor Well Installation <br /> ' Report be prepared and submitted to the City within 45 days of the completion of drilling. Drilling <br /> startup is anticipated to be in late January 2007, however, the time necessary for the Regional Board's <br /> approval of the Work Plan and San Joaquin County's issuance of the Well Permit are beyond the control <br /> of Condor. Delays in any of these items, or delays related to availability of the drilling contractor or <br /> inclement weather, could delay the completion of field activities. If any such delays are encountered, the <br /> City and Regional Board will be notified of the reasons for the delay and a new estimated time for <br /> ' delivery. <br /> If you have any questions or require additional information, please contact Bob Hoagland of Condor <br /> ' 209.532.0361 or Warren Shannon of the City 209.239.8433. <br /> Respectfully submitted, <br /> CONDOR EARTH TECHNOL967ES,INC. <br /> Robert .Hoaglan <br /> Registered Geologist(CA No.485 1) *1 <br /> �qTf OF CP��F� <br /> ' P:\4000_Pd\4654C\Work Plan\Work Plan Final 120806.doc <br /> 1 <br /> 1 <br /> ' CONDOR <br />