Laserfiche WebLink
1. <br /> I, Section 6 <br /> SCHEDULE <br /> This subsurface investigation will be initiated when PG&E receives regulatory approval of this workplan, <br /> lpermission to access adjacent private properties is acquired, the necessary permits are obtained, and <br /> underground utilities are located. We estimate that the field work can be completed in one week; laboratory <br /> lresults may take from one to three weeks and data analysis may take three to four weeks. The technical <br /> report will be submitted approximately ten to twelve weeks following completion of field activities. <br /> s <br /> r <br /> 1 cca/03/10/95 08:19 AM(0688brpt.doc/ntw12) 6-1 <br />