Abandonment of Groundwater Monitoring Wells Work Plan Page 3 <br /> Lodi Central Plume Source Area,Lodi,California <br /> March 23,2024 <br /> ➢ CHT, along with the driller will obtain the Groundwater Monitoring Well Abandonment <br /> Permits from the San Joaquin Department of Environmental Health (SJDEH) <br /> WELL ABANDONMENT <br /> Prior to abandonment of the groundwater monitoring wells,the driller will obtain the requisite well <br /> abandonment permits and get approval from the SJDEH of the appropriate methodologies for well <br /> abandonment. All shallow and intermediate zone monitoring wells will be properly abandoned by <br /> over-drilling using an oversized hollow stem augur drills based on the diameter of the wells. For <br /> the 2-inch diameter wells an 8" outer diameter(OD) auger fitted with a 9" bit will be used, while <br /> for the 4-inch diameter wells, a 10" OD auger fitted with a I I" bit will be used to over drill the <br /> well casing. The deep and deeper zone monitoring wells will be abandoned by over drilling with <br /> a sonic drill rig. The over-drilled borehole will be grout sealed under the supervision of a SJDEH <br /> inspector using the tremie system to the target depth following removal of the well casing. <br /> Figure 1 provides the locations of the wells (encircled in red circles / ovals) that are slated to be <br /> abandoned and Table 1 provides the construction details of those wells. <br /> MANAGEMENTOFINVESTIGATIONDERIVED WASTE <br /> To support Investigation-derived waste(IDW)generated during well abandonment activities,soil <br /> cuttings and decontamination water will be stored in UN-rated, 55-gallon steel drums. IDW will <br /> be profiled and disposed off-site in accordance with local, State and Federal regulations <br /> REPORTING <br /> Following completion of the well abandonment activities, CHT will prepare a Well Abandonment <br /> Report that documents and summarizes all the activities performed at the site, including all <br /> laboratory analytical reports and chain-of-custody forms. The Report will be submitted to the <br /> Water Board and uploaded to GeoTracker within four weeks upon completion of the well <br /> abandonment activities. <br /> SCHEDULE <br /> The field work associated with the well abandonment activities is scheduled to commence from <br /> April 9, 2024, and will continue for a period of six (6) weeks. The Project Schedule is based on <br /> current information available; if any unforeseen circumstances such as inclement weather results <br /> in a delay of the proposed scheduled activities, a revised schedule will be submitted to the Water <br /> Board by CHT. <br /> The Report documenting the well abandonment activities will be prepared and submitted to the <br /> Water Board within four (4) weeks of completion of field activities. A copy of the report and <br /> associated borehole information will be uploaded to GeoTracker. <br /> 581 MONTEGO TERRACE,SUNNYVALE,CA 94089 TEL:415-424-3009 <br />