Natalia Subbotnikova [EH]
<br />From: Baier, William <bbaier@sjgov.org>
<br />Sent: Wednesday, April 4, 2018 7:12 AM
<br />To: Natalia Subbotnikova [EH]
<br />Cc: Garcia, Wilfrido; Chandra, Joyesh; Acevedo, Juan; Bahadori, Taj; Carroll, Michael; Turner,
<br />Tim; Baker -Warren, Joan; Thompson, Jack; Chavez, Diego; Constantino, Roy
<br />Subject: FW: Module 5B Refuse Placement
<br />Good Morning Natalia, please see emails below, once weather permits and 5 B is dry enough to enter safely we will
<br />resume filling this module.
<br />From: Chandra, Joyesh
<br />Sent: Tuesday, April 03, 2018 3:58 PM
<br />To: Baier, William <bbaier@sjgov.org>; Garcia, Wilfrido <Wgarcia@sjgov.org>
<br />Cc: Bahadori, Taj <tbahadori@sjgov.org>; Reno, Desi <dreno@sjgov.org>; Chavez, Diego <dgchavez@sjgov.org>;
<br />Thompson, Jack <jthompson@sjgov.org>; Turner, Tim <tfturner@sjgov.org>
<br />Subject: Module 5B Refuse Placement
<br />mmm
<br />FYI
<br />The water board has now allowed placement of refuse in Module 513 at North County Landfill. See email
<br />below.
<br />JOYESH CHANDRA
<br />SAN JOAQUIN COUNTY I PUBLIC WORKS DEPARTMENT I SOLID WASTE DIVISION
<br />PH:(209) 468-3066 1 Fax:(209) 468-3078
<br />From: DelFrate, Todd @Waterboa rds <Todd. Del Frate@waterboards.ca.goy>
<br />Sent: Tuesday, April 03, 2018 3:40 PM
<br />To: Isham, Julian <Julian.lsham@aptim.com>; Bahadori, Taj <tbahadon@s gov.org>; Chandra, Joyesh
<br /><Jchandra a s ov.org>; Acevedo, Juan <igacevedo@sigov.org>; Carroll, Michael < carroll sigov.org>
<br />Cc: Easter, Daniel <daniel.easter@aptim.com>; Tremblay, Cassandra <cassandra.tremblay@apti.com>; Hold,
<br />Howard@Waterboards<Howard.Hold@waterboards.ca.gov>
<br />Subject: RE: San Joaquin County's North County Landfill
<br />J.C. and others, staff has reviewed the North County Sanitary Landfill documents. As requested in the letter dated 6
<br />March 2018, following installation of wells G-56, G-10, and G-11, San Joaquin County has performed the following:
<br />? Installed wells G-513, G-10, and G-11,
<br />? Developed wells G-513, G-10, and G-11 (submitted well development logs)
<br />? Surveyed the Top of Casings of the newly installed wells,
<br />? Measured depth to groundwater in the new wells on 29 March 2018 (submitted depth to groundwater field logs
<br />with top of casing elevations),
<br />? Prepared a Potentiometric Map using groundwater data from the newly installed wells and other existing wells
<br />onsite,
<br />? Determined groundwater flow direction from groundwater measurements taken on 29 March 2018,
<br />? Conducted initial sampling of groundwater from wells G-513, G-10, and G-11 (provided the chain of custody as
<br />proof of requested analysis including 5 -year COCs),